The following table shows the label and description for 5400R zl2 switch with LED status as ON:
Label
1
2
3
When the module is installed properly and the switch is powered on, or the module is installed
when the switch already has power, the module undergoes a self test that takes a few seconds.
You can use the LEDs to determine that the module is installed properly and has passed the self
test, as described in the "LED Behavior" table below.
Table 1 LED Behavior
LED
Module Status
Test
Fault
Link and Mode (on the
modules)
Error Condition
If the Link LED on the module is flashing orange and the Fault LED on the switch is on, then
there is a fault condition on the port with the flashing orange LED. The module letter, on the
Management Module corresponding to the module with the flashing orange LED will also be
flashing simultaneously.

Connecting the Network Cables

Connect the appropriate network cables to the module's ports as shown in the table below. For
more information on the cable specifications, see "Cabling and Technology Specifications" in
Cabling and Technology
Module
10/100/1000–T PoE zl Module
16
Installing the Modules
Description
Fault LED
Module Link and Mode LEDs
Module Status LEDs
Display for a Properly Installed Module
(for the slot in which you are installing the module) The LED goes ON as soon as
the module is installed and the switch is powered on, and stays ON steadily.
ON briefly while the module is being tested, then OFF.
NOTE:
If the switch was powered off while the module was installed, when the
switch is powered on, the Test LED will stay ON for the duration of the whole switch
self test.
OFF
For a module that is installed when the switch is already powered on (hot swap), all
the Link and Mode LEDs on the module go ON for approximately 3 to 10 seconds,
then OFF for 5 to 10 seconds depending on the module. Then, the Test LED on the
switch goes OFF.
If the module is already installed when the switch is powered on or reset, the process
described above occurs approximately 30 seconds after the power on or reset, during
which the switch is being tested.
Specifications.