Reading Back the AS Parameter Settings
If parameters which are not in the configuration have been set in the AS, you will be able to
read these settings back into the project.
Parameters will be overwritten
Please note that the parameters in the configuration will be overwritten. The decision
concerning whether to use this function will depend on the nature of the system involved and
must be made by the skilled personnel with responsibility for the system.
1. Open your PCS 7 project in SIMATIC Manager.
2. In the component view, select the chart folder of an AS.
3. Double-click on any chart.
The CFC editor opens.
4. Select the menu command Chart > Read Back.
5. Select the entries "Program on the CPU" and "Only data relevant for operator control and
monitoring" in the "Read Back" dialog box.
6. Click "OK".
The read-back process begins.
7. Perform steps 2 to 6 for the automation systems whose current parameters you require.
Backing Up OS Data
If you want to operate the OS server on a newly installed PC following the software update,
we recommend you back up the OS project of the OS server.
By default, the configuration data and the archive data of the OS are stored in the OS project
of the OS server.
To back up data, compress the project paths in this folder. Save the backup on a suitable
medium.
SIMATIC PDM
SIMATIC PDM configuration data is included automatically in the backup of a SIMATIC project.
Software update without utilization of new functions
Service Manual, 03/2016, A5E36200133-AA
CAUTION
Preparing for the software update
5.2 Preparatory tasks