Further details regarding the individual steps
A Turbulators (see page 17)
Checking the expansion vessel and system pressure
Commissioning, inspection, maintenance
A
fA
Note
Please observe expansion vessel man-
ufacturer's instructions.
Carry out this test on a cold system.
1. Drain the system until the pressure
gauge indicates "0" or close the cap
valve on the expansion vessel and
reduce the pressure in the expansion
vessel.
2. If the pre-charge pressure of the
expansion vessel is lower than the
static system pressure, top up with
nitrogen until the pre-charge pres-
sure is 0.1 to 0.2 bar (10 to 20 kPa)
higher.
(cont.)