Door Switch; Roller Latch Assembly (Independent Doors) - Vulcan-Hart VC5ED Service Manual

Full size electric convection oven
Hide thumbs Also See for VC5ED:
Table of Contents

Advertisement

VC5ED FULL SIZE ELECTRIC CONVECTION OVEN - REMOVAL AND REPLACEMENT OF PARTS
NOTE: Check data plate on motor for wiring
schematic. The motor must rotate clockwise when
viewed from the shaft end.
Fig. 15
11. Slide blower onto motor shaft until hub is flush
with end of shaft then tighten bolts.
12. Adjust motor position until blower is parallel to
motor mounting plate, Refer to: BLOWER
ADJUSTMENT.
13. Position motor mounting plate on the rear wall
and secure with screws and washers.
14. Replace the baffle panel.
15. Remove cardboard from the bottom of the oven
cavity.
16. Check oven for proper operation then replace
rack guides and racks.

DOOR SWITCH

electrical power to the machine and
follow lockout / tagout procedures.
1.
Remove BOTTOM FRONT COVER.
2.
Unscrew nut (Fig. 16) holding door switch.
3.
Pull door switch and washer out through bottom
panel opening.
F45652 (0217)
Disconnect the
Page 10 of 31
Fig. 16
4.
Disconnect lead wires to door switch.
5.
Reverse procedure to install replacement switch.
ROLLER LATCH ASSEMBLY
(INDEPENDENT DOORS)
electrical power to the machine and
follow lockout / tagout procedures.
1.
Remove the screws that attach roller latch
assembly to door.
Disconnect the

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents