DEFINITY Enterprise Communications Server Release 6
Installation and Test for Compact Modular Cabinets 555-230-128
1
Install and Cable the Cabinets

Activate and Administer the System

Activate and Administer the System
NOTE:
The Release 6 CMC is a PPN cabinet only. Cabinet A is the control carrier and
Cabinets B and C are port carriers.

Power Up System

Single Cabinet Installations
1. Insert the translation card into the slot in the TN798 Processor circuit pack.
2. Fully seat the 650A Power Unit in the cabinet.
3. Set the circuit breaker at the AC load center to ON. This starts the system
reboot process. In about 2 minutes, verify the screen displays: Login:
Multi-Cabinet Installations
1. Insert the translation card into the slot in the TN798 Processor circuit pack.
2. Set the circuit breakers at the AC load center to ON.
3. Insert the power supplies into the port cabinets.
4. Insert the power supply into the control carrier. This starts the system
reboot process. In about 2 minutes, verify the terminal screen displays:
Login:

System Administration

NOTE:
An "init" login is required to perform the following. Contact the regional
CSA (Customer Software Associate) to assign the Offer Category option.
Maintenance capabilities to initialize the system and access to either an
internal or external modem are the only command options available until
the Offer Category option is set.
NOTE:
Power up the port carriers first and the control carrier last.
Issue 3
May 1998