Cross-Over Gaskets; Intake Manifold Flange Gasket Alignment; Intake Manifold Bolt Tightening Sequence - Dodge 2001 Ram 1500 Owner's Manual

Table of Contents

Advertisement

9 - 54
ENGINE 3.9L
INTAKE MANIFOLD (Continued)
(3) Apply Mopar
GEN II Silicone Rubber Adhe-
sive Sealant, or equivalent, to the four corner joints.
An excessive amount of sealant is not required to
ensure a leak proof seal. However, an excessive
amount of sealant may reduce the effectiveness of
the flange gasket and cross—over gaskets (Fig. 68).
The sealant should be approximately 5 mm (0.2 in)
in diameter.
(4) Install the front and rear cross-over gaskets.
Fig. 68 Cross-Over Gaskets
1 - FRONT CROSS-OVER GASKET
2 - REAR CROSS-OVER GASKET
(5) Using a new gasket, install the throttle body
onto the intake manifold (Refer to 14 - FUEL SYS-
TEM/FUEL
INJECTION/THROTTLE
INSTALLATION).
(6) Carefully lower intake manifold into position
on the cylinder block and cylinder heads. After intake
manifold is in place, inspect to make sure seals are
in place.
(7) Install the intake manifold bolts and tighten as
follows (Fig. 70):
• Step 1. Tighten bolts 1 and 2 to 8 N·m (72 in.
lbs.) Tighten in alternating steps 1.4 N·m (12 in. lbs.)
at a time
• Step 2. Tighten bolts 3 through 12 to 8 N·m (72
in. lbs.)
• Step 3. Check all bolts are torqued to 8 N·m (72
in. lbs.)
• Step 4. Tighten all bolts in sequence to 16 N·m
(12 ft. lbs.)
• Step 5. Check all bolts are torqued to 16 N·m
(12 ft. lbs.)
Fig. 69 Intake Manifold Flange Gasket Alignment
1 - FLANGE GASKET
2 - ALIGNMENT TABS
3 - CYLINDER HEAD GASKET
BODY
-
Fig. 70 Intake Manifold Bolt Tightening Sequence
BR/BE

Hide quick links: