Entrance Ways
Measure the entrance ways; they must be wide enough to accommodate the press and the largest feeder and finisher in the
configuration (see Weights and Dimensions section). Is there proper clearance?
If No, try another entrance or the site must be modified.
Stairs
Are there stairs anywhere in the delivery path?
TIP:
If there are any stairs in the delivery path, the Carrier Delivery Site Inspection must be performed prior to delivery
commitment.
 
WARNING:
The Xerox press should never be up-ended or serious damage will result.
Elevator Requirements
Elevator Weight Requirements
An elevator capacity of 1200 lb. (545 kg) or more is required to move the print engine and print server for an installation. If the
elevator capacity is not adequate, options may exist for elevator modifications. Please contact the on-site maintenance support
for more information on this process.
Does the elevator capacity equal or exceed 1200 lb. (545 kg) capacity
If no: Determine whether modifications can be made to the elevator to increase its maximum weight capacity to 1200 lb. (545
kg). If modifications cannot be made, the elevator cannot be used.
Elevator Width Requirements
The elevator width requirements include the doorway entrance and the interior area. The elevator must meet the following width dimensions:
Elevator Doorway Entrance Width
Minimum 31 in/787.4 mm
Elevator Interior Width
Minimum 34 in/863.6 mm
Measure the elevator entrance dimensions. Is there sufficient space at the elevator opening?
If No and the elevator opening is too narrow, determine whether there is another means of transporting the press modules and
installation location.
Installation Site Space Requirements
Is the site cleared and ready for installation?
If No: When will the site be cleared?
____________________________________________________________________________________________________
Ensure that it will be cleared and ready prior to machine installation.
Is proper power available?
If No: When is power scheduled to be installed?
___________________________________________________________________________________________________
Is the date prior to machine installation?
Customer Expectation & Installation Guide
Yes
No
Yes
No
?
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No