Injection
11
Electric fan remote control
Check the resistance at the injector ends: 14.5 ± 5% Ohm
Check the efficiency of 10 A fuse N° 4 injection
load .
Check the efficiency of 7.5 A fuse No. 9 key-con-
trolled control unit power supply.
Check the efficiency of the injection load remote
control: Check the resistance of the energising coil
between pins 86 and 85: 40 to 80 Ohm
Apply a voltage of 12V to pins 86 and 85; make
sure that there is continuity between pins 30 and
87 of the remote control.