Starting the heating system
The initial start-up and matching of the control unit to local conditions and
the structural characteristics of the building must be carried out by your
heating contractor.
A
1. Check the pressure of your
heating system on the pressure
gauge A:
If the needle is below the red
marker, the system pressure is too
low
in which case, top up with
water or contact your heating
engineer.
2. Open the shut-off valves in the oil
supply pipes (at the oil tank and
filter) or open the gas shut-off
valve.
3. Switch on the mains supply, e.g.
at a separate fuse or a mains
isolator.
4. Switch on the main ON/OFF
switch "8"; standby mode is then
indicated by the green lamp (ON
lamp); shortly after the display will
indicate the boiler temperature
(see page 6).
Your heating system and, if
installed, your remote control unit
are now ready to operate.
Start-up/shutdown
15