Mounting the boiler and making the connections

Filling the siphon with water

Balanced flue connection
Connecting several Vitodens 050-W
to a shared flue system
Adjust the burner setting of each con-
nected boiler to match the flue system.
See page 31.
Do not carry out commissioning until
the following conditions are met:
■ Free passage through the flue gas
pipes.
■ Flue system with positive pressure is
gas-tight.
Installation sequence
Pour at least 0.3 l of water into the flue
outlet.
!
Please note
During commissioning, flue gas
may escape from the condensate
drain.
Always fill the siphon with water
before commissioning.
Connect the balanced flue pipe.
During installation and positioning of the
flue system, observe Part J of building
regulations and BS 5440.
Flue system installation instruc-
tions
■ Apertures for ensuring sufficient com-
bustion air supply are open and cannot
be closed off.
■ Applicable regulations on installing
and commissioning flue systems have
been followed.