Step 1:
Rough Opening and Framing Requirements
This section gives requirements for framing and rough opening clearances. Masonry or concrete openings must be
lined with a treated wood product (wood buck). You must fasten the buck to the masonry opening in a fashion that
will withstand conditions which would be encountered under the certified and advertised DP ratings for this window.
The structural integrity of this installation is only as good as the bond between the wood buck and the masonry
opening. For more details, contact your Marvin representative.
NOTE: Wood buck material thickness may vary. Illustrations show a 1/2, plywood and 2 x 4 buck. Installations
using material less than 2, nominal material must use the jamb screw method of attachment and use 3/16, concrete
anchors.
Treated
2 x 4 buck
Construction
adhesive
Masonry
anchor
1/2" treated
plywood
Figure 1: Preparing openings for concrete block openings.
1. On concrete block, masonry, or similar situations, line
the sides, head jamb, and sill with treated lumber.
Attach the lumber to the masonry opening with
construction adhesive and masonry anchors which
should penetrate the masonry opening by at least
1"−1 1/2"
. See figure1a and 1b.
(25−38)
2. For standard wood frame construction, prepare the
opening following local codes, ASTM E2112−1, or fol-
low the steps in the "Continuous Air Barrier
Systems" section.
3. If rigid panning is used, place a bead of silicone or
construction adhesive over any fasteners used to
hold the panning to the sill.
19970019
2012−04−10
(a)
(b)
4
(c)
NOTE: If your installation requires screwing through
the sill for structural purposes, place a bead of sealant
where the screws will penetrate the rigid sill panning.
4. The window frame must not come in contact with
treated lumber. If you will not be using rigid panning
or shimming at the sill, apply a barrier such as a self
sealing adhesive flashing to the rough opening sill.
See figure 1 c.
Adhesive
flashing
Window Installation
StormPlus and Structural Installations