Servicing - Warmworld FFC 30/60 Installation & Service Instructions Manual

Condensing boilers natural gas only
Table of Contents

Advertisement

Servicing

Health and Safety Statement :
This product contains no asbestos.
Routine
To ensure continued efficient operation of the
appliance it is recommended that it is checked
and serviced at regular intervals.
The frequency of servicing will depend upon
the particular installation and usage but in
general once per year should be adequate.
It is law that any service work should be carried
out by Corgi registered personnel.
1. Clean burner and combustion chamber.
2. Check pilot and burner gas supply.
3. Check condition of ignition sensing probe.
4. Check boiler pipework joints for leaks.
5. Check the case seals.
6. Check condensate pipework for leaks.
7. Check heat exchangers, and the flue and air
duct are clear of any obstruction, and not leak-
ing.
8. Check the Fan and its seal.
9. Check and clear the condensate exit on the
secondary heat exchanger by removing the
Condensate Outlet and the Inspection
Cover (Fig. 10).
10. Check and clear the condensate syphon.
Follow the procedures given in Changing Com-
ponents for parts removal in addition to the fol-
lowing notes.
1.Heat Exchangers
Remove the panel in front of the secondary
heat exchanger to gain access to inner inspec-
tion panels on the secondary and to view the
primary (the lowest inspection panel also gives
a view of the primary). Also view from beneath
the primary. Clean as required. If in doubt,
drain the system and remove for inspection.
2.Condensate Syphon
With a suitable bowl to catch the water, un-
screw the drain-cap(s) on the underside of the
Syphon trap and drain the water. Remove any
solids and replace cap(s). (Fig 12)
Condensing Boiler
CHANGING COMPONENTS
THERE ARE NO REPAIRABLE ITEMS, IF NOT
WORKING AN ITEM MUST BE REPLACED.
The boiler is in two major sections, the Case,
and the Electrical Tray, The Major Components
Diagram shows where the items are to be
found. (pages 23-24)
Behind the Electrical Tray
1. Control Board.
2. Gas Valve.
Behind the Case
3. Fan.
4. Air Pressure Switch.
5. Flue Thermostat.
6. Control Sensor.
7. Overheat Cut-off Device.
8. HT Lead.
9. Pilot Assembly.
10. Burner.
11. Main Injector.
12. Combustion Chamber Insulation.
13. Primary Heat Exchanger.
14. Secondary Heat Exchanger.
Servicing behind the Electrical Tray
To Remove the Electrical tray
Disconnect the electrical supply from the
boiler and system.
Slide the Electrical Tray forward a short way,
then lower. Remove the cover over the
components.
DO NOT STRAIN THE CABLES, USE
THE SUPPORT PROVIDED.
1. Control board
Remove the Control knob.
Lower the Electrical Tray.
Remove the single screw that retains the
inner cover.
Pull off the HT Lead, Multipole plug, and the
Gas Valve lead, at the Valve.
Slide back the Electrical Chassis and re-
move.
Undo the Earthing screw and then pull off
the 4 and 10 way Molex connectors.
Remove the bracket for the potentiometer.
Slide the Control Board out of the chassis.
Transfer the pcb support to the new board.
Replace the Control board.
Re-assembly is the reverse.
20
06/06/01

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ffc 65/80

Table of Contents