Checkout Procedure - Temp-O-Matic TMP Multi-Position User Manual

Oil
Table of Contents

Advertisement

TMP
– Furnace Manual
Oil Furnaces
8

Checkout procedure

Furnace selection
..1. Heat loss ............................... BTU/h at ............
design temperature.
..2. Furnace model .......................................................................
output .......................... BTU/h.
..3. Burner model ........................................................................
nozzle: ............. gph ................
..4. Burner pump pressure ........................................ psig.
Furnace installation
..5. Is furnace level?
..6. Are return and supply ducts securely attached to furnace?
..7. Are fuel filter and fuel lines installed and inspected as per
the burner manual?
..8. Are furnace and burner wired as per the wiring diagram?
..9. 120 VAC wiring: type ................ size ................ AWG.
Vent and combustion air
..10. Was existing chimney/vent system inspected and found in
proper condition?
..11. Was new vent piping installed and sealed as required?
..12. Was vent sizing checked against furnace manual and
codes?
Ductwork
..13. Was duct sizing checked against furnace manual and/or
ACCA Manual D?
..14. Were supply and return registers checked for size based on
airflow?
..15. Were balancing dampers installed as needed?
..16. Was ductwork sealed and insulated as needed?
Furnace model
__________________________________________________
Serial number
_______________________________________
Installation instructions have been followed.
Checkout sequence has been performed.
Above information is certified to be correct.
Information received and left with owner/maintenance person.
Installer ______________________
18
o
F outdoor
o
type............... .
Installation and service certificate
________________________
(company)
Furnace operation
.. 17. Is a / Are clean air filter(s) in place?
.. 18. Was temperature rise through furnace checked (not to
o
exceed 85
F) and blower speed adjusted if necessary?
.. 19. Was thermostat heat anticipator set per wiring diagram?
.. 20. Was burner started and tested per burner manual?
.. 21. Is there proper draft and burner flame? Were final
adjustments made with combustion test equipment?
.. 22. Was air purged from oil piping and piping checked for leaks?
.. 23. Was burner sealed to furnace and nuts tightened? Was
burner harness securely plugged in?
Obtain gas-tight seals at burner flange, cleanout
plates and/or flue collector box to prevent possible
flue gas leakage and carbon monoxide emissions,
leading to severe personal injury or death.
.. 24. Was Limit Control tested per "To start up" in this manual?
.. 25. Was furnace cycled with thermostat? Raise to highest
setting and verify furnace goes through normal start up
cycle. Lower to lowest setting and verify furnace goes off.
.. 26. Were several operating cycles observed for proper
operation?
.. 27. Were room thermostat(s) set to desired room temperature?
After installation
.. 28. Was "Installation and service certificate" (below) filled out?
.. 29. Was Owner's information in this manual reviewed with
owner or maintenance person and the person instructed to
keep the manual for future reference?
.. 30. Were all instruction manuals placed near the furnace for
future reference?
Series
Date installed
_____________________________
_____________________
(address)
________________________________________________
(installer's signature)
_______________________
(phone)
670-000-004/1010

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents