Power On Checkout.
• Once the unit is properly mounted, you may begin the checkout procedure. First,
insure that all the equipment to be powered by the unit is installed.
• Install the battery fuse, located on the right side of the unit just below the distribution
panel.
• Attach the supplied AC power cord to the left side of the DP140e.
• Plug the DP140e power cord into the AC commercial power outlet made available for
this purpose. The Battery Charge Status Indicator will be either solid green or flashing
green and the battery test indicator should be solid green.
• Connect the equipment to the distribution connector for power output on the right side
of the unit.
• You should have power indicator on the equipment you connected to the power
supply.
• Your DP140e supply should now be functioning properly in addition to the equipment
you have connected.
• Battery Test: When the battery is fully charged (Battery Charge Status LED
constant green), press the Manual Battery Test switch. Wait five seconds then
verify that the Battery Test Status LED is green. (The Manual Battery Test is only
available when the Power Unit is has completed charging the battery pack).

Repair and Maintenance

The DP140e power supply has been designed to operate unattended and with low
maintenance overhead for extended periods of time. However, the rectifier output
voltage should be check on an annual basis and adjusted if outside of the recommend
range of 54.4 to 55.5V