Pentair Mi Series Installation, Maintenance And Operation Manual page 41

Mineral insulated (mi) series heating systems
Table of Contents

Advertisement

is below design
Corrective actions
1
Remove wet insulation and replace with dry insulation and
secure it
2
Confirm compliance with system design. (If valve, flange,
and pipe support types and quantities have changed,
additional heating cable may be required.)
3
Reset temperature controller
4
Contact your Pentair Thermal Management representative
to confirm the design and modify as recommended
5
Confirm that sensor is in the correct location
6
Verify temperature of fluid entering pipe
Corrective actions
1
Repair electrical supply lines and equipment
2
Confirm wiring using the normally closed (N.C.) terminals
so that contacts close with falling temperature
3
Check the reason for the limiter trip. Resolve problem and
reset limiter.
4
Repair or replace heating cable
5
Verify installation as per design and replace cable if
necessary
6
Verify voltage and connect to proper voltage if necessary
3
Look for crushed or damaged insulation and cladding
along the pipe
4
If after 1, 2 and 3 above the fault has not been located,
then consult Pentair Thermal Management for further
assistance
41