Multiple boiler installations
Sequencing multiple ECO boilers
1. Use a multiple-boiler controller, such as the Weil-McLain BCP,
BMC or BSC, to sequence boilers. Locate temperature sensors as
required in the controller manual.
Easy-Fit® piping installation
1. Main header and Easy-Fit® Manifold pipe sizing.
a. Size system piping as required for the flow.
b. Install tees or crosses in the system piping for Easy-Fit® mani-
folds as shown in Figure 55 or Figure 56. Size manifolds to
handle total connected boiler output as shown.
2. Provide connections in main header for Easy-Fit® manifolds as
close as possible to the midpoint of multiple boilers.
a. Use tees for four or less boilers, as in Figure 55.
b. Use either tees (Figure 55) or crosses (Figure 56) for five or
more boilers.
3. Manifold placement:
a. To alternate spacing for supply and return lines to boilers,
reverse the short-end and long-end of the manifolds as shown
in Figure 55 and Figure 56.
b. Return manifold must be on the return side of the main and
supply manifold must be on the supply side of the main. Draw-
ings in this manual show flow in system main from right to
left. For system flowing left to right, reverse the locations of
the manifolds accordingly.
4. Connect from Easy-Fit® manifold branches to boiler supply and
return connections using copper or steel pipe, sized for the required
flow rate.
It is recommended to pipe to boilers such that the first
boiler connection off the return manifold is piped
to the furthest connection on the supply manifold
from the main header. See Figure 57, page 52 and
Figure 58, page 53 for example.
5. Install an isolation valve on the supply and return of each boiler
as shown in the piping diagrams in this manual. Some local codes
may require the use of individual water level controls and limits
on each boiler because isolation valves are installed.
6. Install main system air eliminator and primary circulator in sup-
ply piping as shown in piping diagrams. Place expansion tank on
suction side of system circulator as shown.
7. Install system accessories as shown in drawings.
8. Piping recommendation drawings:
a. Figure 55 and Figure 56 show details of Easy-Fit® manifolds.
b. Figure 57, page 52
is a schematic piping drawing showing the
locations of typical boiler piping and system piping, including
limits and other devices often required by local codes.
9. If desired, other primary/secondary piping arrangements can be
used.
Part number 550-142-122/0513
— Boiler Manual
(continued)
Single-sided EZ-Fit Header connection
Double-sided EZ-Fit Header connection
51

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

110155Eco 110Eco 155

Table of Contents