Exhaust system quad-tip 2008 ford power stroke 6.4l turbo-diesel f250/f350 trucks

Advertisement

Figure 4
FACTORY
LEAF STOP
10.
Install the Y-pipe over the
intermediate pipe as shown in
Figure 1. Install clamps onto each
Y-pipe outlet.
11.
Locate the two slots on the rear
diverside frame rail and install the
supplied Banks hanger bracket using
the supplied hardware. Be sure the
hanger pin is align parallel to the frame
rail and torque the hardware to 48ft-lb.
See Figure 4.
12.
Install the supplied rubber
insulator onto the Banks hanger
bracket.
8
96547 v.1.0
BANKS
7/16"
HARDWARE
FORWARD
BANKS
HANGER
BRACKET
FACTORY
FRAME
SLOT
BANKS
RUBBER
INSULATOR
BANKS
DRIVER SIDE
TAILPIPE
13.
Install the driver-side tailpipe onto
the left Y-pipe outlet. Install the driver-
side tailpipe hanger into the vehicle
rubber insulator. Position the rubber
insulator as shown in Figure 5.
14.
Install the passenger-side tailpipe
onto the right Y-pipe outlet. Install the
passenger-side tailpipe hanger into the
vehicle rubber insulator. Position the
rubber insulator as shown in Figure 3.
15.
Loosen and move the spare-tire
to the rear of the vehicle and center
between the dual tailpipes. Securely
tighten the spare tire so that it is
retained in place see Figure 6.