This assembly instruction contains important information on assembling roller shut- ters as well as important safety instructions. The assembly operation may only be carried out by specialized staff of Schanz Rollladensysteme GmbH or technicians especially authorized by Schanz Rollladen- systeme GmbH.
Page 2
Put on the cover and screw it back. Assembling / Installation / Working on the facade Each roller shutter is individually manufactured according to your window shape and size and must only be installed by Schanz Rollladensysteme GmbH or technicians especially authorized.
Page 3
MAL Wiga Star-Typ DSI_englisch Version: 09.01.25 Page 3 of 12...
Page 4
Cord Guidance MAL Wiga Star-Typ DSI_englisch Version: 09.01.25 Page 4 of 12...
Page 5
Description of the basic procedure Step No. Operation Note Check Check delivery for completeness Delivery is complete Compare the goods with delivery note Screw substructure to conservatory profile Mount at right with appropriate fixing material angle Lay sealants at the drill holes between the conservatory frame and aluminium profile Mount the bracket at a right angle to the Mount at right...
Page 6
Step No. Operation Note Check Pulling the cord through The cord is fixed in the end rail Guide the cord over the the cord roll in the panel Guide the cord through the guide rail over the cord roll and to the cord pulley Pre-assemble cord Only perform -Only with mechanical motor-...
Page 7
Step No. Operation Note Check Attach guide rails Do not damage Put the guide rails on the box the cord Mounted at right Adjust the correct position with an angle angle Screw the guide rails with appropriate fixing material to the aluminium profiles according to the number of fixing holes on the guide rails Attach cord...
Page 8
Step No. Operation Note Check Attach the guiding support(s) Insert the guiding support(s) between roller shutter jacket and the back panel until the bottom of the box and align it Screw the guiding support(s) with appropriate fixing material to the aluminium profiles according to the number of fixing holes on the guiding support(s)
Page 9
Step No. Operation Note Check Put on panel (without cord roll), adjust it and screw it with two short tapping screws to the guide rail For attaching the panel the screw ISO 7049 – A2 3,9 x 9,5 is needed Note: Always pre-drill the holes Rivet the panels Do not damage...
Page 10
Arbeits- Arbeitsvorgang Bemerkungen Prüfungen gang Nr. Attach Roller shutter box Unscrew the screws of the box lid and open the roller shutter box Screw the roller shutter box on the left and the right side through the side part and back panel with appropriate fixing material with the substructure.
Page 11
Step No. Operation Note Check Note: It is recommended to conduct the following operation after the setting of the roller shutter Attach the stabilizer(s) A spacer sleeve is being added between guiding support and panel Do not damage Pre-drill a hole for the countersunk the cord screw through the panel in the aluminium profile, countersink it and...
Need help?