WARNING:
!
FIRE OR EXPLOSION HAZARD
Failure to follow safety warnings exactly could result in serious injury,
death or property damage.
Be sure to read and understand the installation, operation and service
instructions in this manual.
Improper installation, adjustment, alteration, service or maintenance can
cause serious injury, death or property damage.
Do not store or use gasoline or other flammable vapors and liquids in the
vicinity of this or any other appliance.
WHAT TO DO IF YOU SMELL GAS
·
Do not try to light any appliance
·
Do not touch any electrical switch; do not use any phone in your building
·
Leave the building immediately
·
Immediately call your gas supplier from a phone remote from the
building. Follow the gas supplier's instructions.
·
If you cannot reach your gas supplier, call the fire department.
Installation must be performed by a qualified installer, service agency or gas
supplier
.
This manual must be kept with the gas burner for future reference.
Heatco Inc.
50 Heatco Court
Cartersville, GA 30120
GS-MAN-E-0

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the GENESIS GS Series and is the answer not in the manual?

Questions and answers

Summary of Contents for heatco GENESIS GS Series

  • Page 1 If you cannot reach your gas supplier, call the fire department. Installation must be performed by a qualified installer, service agency or gas supplier This manual must be kept with the gas burner for future reference. Heatco Inc. 50 Heatco Court Cartersville, GA 30120 GS-MAN-E-0...
  • Page 2: Table Of Contents

    The information provided in this manual applies only to the gas burner, its installation in an appliance, operation, maintenance and service. Refer to the appliance manufacturer’s instructions for information related to all other components. Table of Contents Inspection on Arrival Model Number Identification Specifications and Capacity Ratings and Electrical Ratings...
  • Page 3: Model Number Identification

    Model Number Identification...
  • Page 4: Specifications And Capacity Ratings And

    Specifications and Ratings Maximum Input Minimum Input Minimum Input Maximum Inlet Minimum Inlet Burner Model (Btuh) Natural (Btuh) Propane (Btuh) Pressure Pressure GS 1 1,500,000 35,000 70,000 1 PSI 7 "W.C. GS 2 2,500,000 55,000 96,875 1 PSI 7 "W.C. GS 3 3,750,000 93,750...
  • Page 5: General Gas Burner Information

    Standard Heatco GS burner models require at least 7” w.c. inlet gas supply pressure to maintain the maximum rated firing rate. Larger burner models require up to 1 PSI. Some gas train requirements can increase the pressure drop of the gas train (hydraulic valves, redundant valves, specific components, etc.).
  • Page 6 Standard burners are shipped as natural gas or propane gas, as indicated on the burner rating label. Heatco GS burner models can operate on either gas with only a gas orifice and manifold pressure adjustment. Field gas conversions need to contact the manufacturer for orifices and labels that are to be applied on the burner showing that the burner has been converted to a different gas other than what is stated on the ratings label.
  • Page 7: Burner Dimensions

    Burner dimensions GS 1 GS 2...
  • Page 8 GS 3...
  • Page 9: Burner Mounting

    Burner Mounting Mount the GS burner assembly to the intended appliance by using the supplied mounting flange and through bolt design. Depending on the GS burner model, the mounting flange size and callouts will change. Below are figures showing the GS 1, 2, 3, 4 burner standard mounting flange sizes. GS 1 GS 2...
  • Page 10 GS 3 GS 4...
  • Page 11: Gas Supply, Piping, Connections

    Gas Supply, Piping, Connections All Heatco GS burner models come with specifically designed gas trains. It is up to the equipment manufacturer and/or the end user to communicate all gas train requirements at the time of order. These requirements can be but are not limited to gas type, gas supply pressure, gas supply pipe size, gas train standard, installation location, environmental conditions, electrical supply, and local jurisdictions.
  • Page 12: Wiring

    Wiring Heatco GS burner models are pre-wired based on job specifications at the factory. Refer to the wiring diagram shipped with the burner. Electrical hook-ups and installations must be made in accordance with the National Electrical Code, applicable local codes, or any other requirements by an authority having jurisdiction.
  • Page 13: Electrical Supply

    Electrical Supply The gas burner control system requires both line voltage and low voltage circuits with correct polarity, and clean neutral and ground. Line voltage readings between L1 and Neutral as well as L1 and Ground should be within +/- 3 volts.
  • Page 14: Operation And Procedures

    Operation and Procedures The Heatco GS Burner series utilizes a Siemens LMV3 flame safeguard control. The LMV3 is a linkage-less burner management system and is an extremely flexible control with features including but not limited to: fuel-air ratio control and Variable Frequency Drive The Heatco LV Control requires a supply voltage, heat enable signal (binary-contact), and a 4 –...
  • Page 15 2. Required test instruments include: a. Combustion analyzer to measure CO ), CO b. Temperature gage for measuring flue gas temperature (up to 550 oF) and outlet air temperature c. Draft Gauge (or inclined manometer) d. Volt-Ohm-Amp Meter e. DC Micro-Ammeter or DC Voltmeter as required by Flame Safeguard control 3.
  • Page 16: Sequence Of Operations

    Sequence of Operations 1. Turn thermostat or temperature controller to its lowest setting. 2. Turn off gas supply at the inlet gas manual shut-off valve. 3. Turn off power to the unit at the disconnect switch. 4. Remove access panel or open access door to unit vestibule housing the burner. 5.
  • Page 17 14. After confirming the pre-purge settings and timings, the LMV3 will proceed into the ignition cycle. The AZL display will show “Ph 38” Pre-Ignition. 15. The ignition transformer is energized and the pilot gas valve is opened for the 10 second trial. The AZL display will show “Ph 40”...
  • Page 18 19. The main flame must be stable and once the signal is sensed the ALZ display will show “Ph 52” Main Flame Stabilization. 20. Once the ignition sequence is verified, the LMV3 will go into normal operation. The AZL display will show “oP”...
  • Page 19: Operational Matrix

    Table - Operational Matrix...
  • Page 20: Troubleshooting

    Troubleshooting When a lockout occurs, the AZL display that is connected to the LMV3 will alternate between displaying “Loc:c” and Loc:d”. The number listed after “Loc.c” is the error code, and the number listed after “Loc:d” is the diagnostic code. For example, an error code 4, diagnostic code 3 will alternate between displaying “Loc:c 4” and “Loc:d 3”...
  • Page 21: Annual Inspection And Maintenance

    Technical Support can be reached during normal business hours excluding nation (US) holidays in between the operating hours of 8:00am EST – 5:00pm EST. Contact info can be found below: Service: service@heatco.com 770-529-2000 Annual Inspection and Maintenance Annual maintenance of the burner is recommended to ensure trouble free operation.
  • Page 22: Gas Train Leak Test

    your specific burner. The flame rod exposed metal should be clean and free of dirt and carbon. The porcelain must be intact and not cracked. If unsure it is best to replace it. If the flame sensor is a scanner, clean the lens with a clean damp soft rag.
  • Page 23: Warranty And Replacement Parts

    Heatco will repair or provide, at its option, any components which, it finds to be defective, provided that the unit has been operated within its listed capacity, installed in accordance with the furnished instructions, and had an initial startup evaluation performed by a qualified combustion technician.