Page 1
Installation Instructions Trane Rental Service Start-Up and Shutdown - RSGP0900F2 Generator SAFETY WARNING Only qualified personnel should install and service the equipment. The installation, starting up, and servicing of heating, ventilating, and air-conditioning equipment can be hazardous and requires specific knowledge and training.
Page 2
(Global Harmonized System of Classification and compounds have the same potential impact to the Labeling of Chemicals) guidelines for information on environment. Trane advocates the responsible handling of allowable personal exposure levels, proper all refrigerants-including industry replacements for CFCs respiratory protection and handling instructions.
Page 3
Copyright This document and the information in it are the property of Trane, and may not be used or reproduced in whole or in part without written permission. Trane reserves the right to revise this publication at any time, and to make changes to its content without obligation to notify any person of such revision or change.
Page 5
Graphical Display Panel Figure 1. Graphical display panel This control is provided with a graphical display capable of displaying up to 9 lines of data with approximately 27 characters per line. The graphical display is accompanied by a set of six tactile-feel membrane switches that are used by the operator to navigate through control menus and to make control adjustments.
Page 6
Installation/Setup 1. Level the generator using appropriate cribbing and 4. Locate camlock connections on driver side of the front leveling legs. Wheels must be chocked. generator. Important: Ensure the generator is grounded according to local code. 2. Remove ladder from inside of rear door of generator and install on passenger side of generator.
Page 7
3. Press GOVERNING/VOLT REG button. 12. Press the HOME button to return to the main screen. 4. Verify VOLT SELECT is set to the correct voltage (i.e. 480, 240, 208). Important: If voltage is not correct, contact Trane Rental Services. TEMP-SVN005A-EN...
Page 8
Installation/Setup Start-Up 5. Repeat Step 8 Step 12 above to place the generator in RUN MODE RATED. 1. Turn the control knob to MANUAL. 6. Once the generator is running at rated speed, press breaker close button (__\__). The switch icon will change from open (__\__) to closed (__---__).
Page 9
Shutdown Follow the manufacturer's instructions to shutdown all 5. Press the BREAKER OPEN button. equipment powered by the generator. Important: Verify there is no generator load. 1. Press the HOME button. 6. Press the MANUAL RUN/STOP button to shutdown the generator. 2.
Page 10
Shutdown 10. Disassemble/re-stow ladder and hand rail on rear door. TEMP-SVN005A-EN...
Page 12
For more information, please visit trane.com or tranetechnologies.com. Trane has a policy of continuous product and product data improvement and reserves the right to change design and specifications without notice. We are committed to using environmentally conscious print practices.
Need help?
Do you have a question about the RSGP0900F2 and is the answer not in the manual?