FSD-C Series
Installation, Operation and Maintenance Instructions
THESE INSTALLATION INSTRUCTIONS MUST BE READ IN THEIR ENTIRETY
THESE INSTALLATION INSTRUCTIONS MUST BE READ IN THEIR ENTIRETY
BEFORE COMMENCING WORK TO ENSURE COMPLIANCE
BEFORE COMMENCING WORK TO ENSURE COMPLIANCE
Dampers will only be CE marked if:
• Installed as tested
• These instructions are followed
Any non-tested proposals cannot be CE marked.
Before commencing installation, the "Installation Check List" within DW/145
should be referred to. See "Damper Installation Certificate" on page 14.
M A N U FAC T U R E R S O F A I R , FI R E A N D S M O K E C O N T R O L P R O D U C T S

Advertisement

loading

Summary of Contents for Maico BSB FSD-C Series

  • Page 1 FSD-C Series Installation, Operation and Maintenance Instructions THESE INSTALLATION INSTRUCTIONS MUST BE READ IN THEIR ENTIRETY THESE INSTALLATION INSTRUCTIONS MUST BE READ IN THEIR ENTIRETY BEFORE COMMENCING WORK TO ENSURE COMPLIANCE BEFORE COMMENCING WORK TO ENSURE COMPLIANCE Dampers will only be CE marked if: •...
  • Page 2 FSD-C Damper Installation, Operating & Maintenance Instructions FSD-C Damper Installation, Operating & Maintenance Instructions Storage Dampers received on site should be stored in a purpose made storage area, 1 Storage where they can be protected from moisture, dust, and impact damage until Dampers received on site should be stored in a purpose made storage area, required.
  • Page 3 3 Equipment required Equipment and tools will vary dependent upon the fire barrier construction that 3 Equipment required the damper is being installed within. Standard equipment that are normally Equipment and tools will vary dependent upon the fire barrier construction that used for the building of the particular barrier should suffice.
  • Page 4 The opening must be ‘lined out’. Cut size = damper size + (2 x nominal gap size) + (2 x wall board thickness). E.g. for 150mm dia. damper, and 12.5mm wall board, cut aperture should be 195mm (150+(2x10)+(2x12.5)) Mark out position and size of required cut size on the wall. Obscured fixing hole behind No infill required in the void actuator (see 6.11)
  • Page 5 Masonry wall and floor installation (Refer to FSD-C M10) Steel fixings – refer to 6.19 6.12 Preferably, prepare opening whilst building wall/floor, or cut opening if wall/floor already exists. 6.13 Cut size = finished size 6.14 E.g. for 250 dia. damper, cut aperture should be 270mm square (250+20) 6.15 Mark out the position and size of opening on the wall/floor.
  • Page 6 7.2.3 To ease the installation, the drop rods can be joined using a coupling nut and a pair of lock nuts to save having to spin the M10 nuts all the way along the length of the studding to the top cleat. 7.2.4 Upper drop rod length –...
  • Page 7 7.3.5 Cut opening in the FFC material to allow material to pass over damper spigot. It is advisable to cut ‘a cross’ diagonally from the centre of the damper to the inside of the damper case only at this stage, and cut to final size once FFC material is fixed to structure/adjacent fire curtain vertical runs.
  • Page 8 8 Actuator Orientation Change / Replacement If required, the orientation may be changed to +90° or -90° from default ‘in- line-with-duct’. Ensure power to actuator is removed and allow actuator to travel to end position. Unscrew the 8mm AF head screw (central motor retaining screw) and remove the set-point assembly.
  • Page 9 Retighten the retaining screw to approx. 3Nm. Retighten the retaining screw to approx. 3Nm. Re-apply power and check desired open position is attained. 9. 6 Re-apply power and check desired open position is attained. 10 Wiring 9 Wiring 10.1 Refer to electrical specification on back page of this document. Refer to electrical specification on back page of this document.
  • Page 10 Actuator and Thermal Fuse Access/Maintenance/Install zone 11.1 Leave enough room for removal and fitment pf the actuator and thermal fuse. See red and blue zones below. Default: Position 2...
  • Page 11 d and blue zones in the below images. zones in the below images.
  • Page 12 10 Commissioning, Maintenance and Test 12 Commissioning, Maintenance and Test 10.1 Pre-check BEFORE power is established – Check the actuator voltage is 12. 1 Pre-check BEFORE power is established – Check the actuator voltage is suitable for the application. 24V has a grey case, 230V has an orange case. suitable for the application.
  • Page 13: Fault Finding

    12 Fault Finding Symptom Fault Corrective Action Damper not in its No power / incorrect Check supply/terminations Check signal supply ‘normal’ state connections Green LED on the TF tripped. Remove If open circuit, replace probe Thermal Fuse TF from duct, separate (TF) two halves, continuity check the two contacts...
  • Page 14: Electrical Details

    Electrical details 24V (Grey actuator case) 230V (Orange actuator case)
  • Page 15 Damper Installation Certificate DAMPER REFERENCE NO.: DAMPER LOCATION: DAMPER SIZE: Dia (mm) WALL/FLOOR APERTURE SIZE (‘OPENING SIZE’) WIDTH HEIGHT DAMPER INSTALLED BY: ............(Print name) Signature: Company: Date: ACTUATOR ELECTRICALLY CONNECTED BY: ............(Print name) Signature: Company: Date: Actuator mid-point setting (circle if applicable) 30°...
  • Page 16 For purchase orders and order related enquiries, please email: orders@bsb-dampers.co.uk For pricing, technical and general enquiries, please email: enquiries@bsb-dampers.co.uk Website: www.bsb-dampers.co.uk • A member of the Maico group BSB Engineering Services Ltd. reserves the right to modify or withdraw any specification without prior notice that may result from...