Page 1
SUMITOMO ELECTRIC LIGHTWAVE CORP. 201 South Rogers Lane, Suite 100, Raleigh, NC 27610 (919) 541-8100 or 1-800-358-7378 www.sumitomoelectriclightwave.com SEL is a Member of the Sumitomo Electric Industries, Ltd. Group Sumitomo Electric Lightwave reserves the right to improve or modify these specifications without notice.
Page 2
6. Tape Measure the door or cover to avoid pinching hands or 7. IDEAL Wire Marker Booklet (#44-101) fingers. 8. Sumitomo Ribbon Separator Jig 9. 6 – 8ft. Table • Watch out for protruding objects when bending 10. Cable clamps down or standing up near cabinet.
Page 3
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 5.0 Installation of Cabinet 5.2.2 Closing the Door 5.1 Securing the Cabinet to the Floor Turn the door handle in clockwise direction with pushing the door gently. Attach the cabinet on the floor with anchor-bolts M12.
Page 4
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 Note: Be careful not to score entirely through the jacket material which could cut the ripcords. Figure 6 Figure 4 6.1.4 Remove water-blocking tapes and binder strings. 6.1.2 Gently bend the cable around the cut portion until the jacket material separates.
Page 5
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 6.1.6 Cut the slotted core length specified in Note: Assist ribbon/tube identification by grouping Appendix 1. ribbons in 4 tubes per slot for UHFC 1152 fiber. 6.1.7 Make a cut on the slotted core material ex: Tube 1: Ribbons 1-4, Tube 2: Ribbons 5-8, with utility knife and remove with pliers to expose Tube 3: Ribbons 9 -12, Tube 4: Ribbons 13-16...
Page 6
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 For 1152 Breakout number all tubes 6.2.5 (When routing fibers through tubes) Touch consecutively 1 – 24 at both end of the tubes. the slotted core against the cable stopper and, Insert ribbons into each tube that matches the install strength member in the cable stopper.
Page 7
(1728-F) is similar to the procedure for HSX (1152). Install from back side to front side **In case of HSX(1152), 24 tubes / unit ×6 splice units (3 tubes / tray×8 trays, or 4 tubes / tray×6 trays). Breakout kit No.1...
Page 8
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 8.0 Installation of Transportation Tube and Splicing 8.1 Removing the Splice Tray 8.1.1 Remove the splice tray and put it on the workbench approx. 3.28ft. (1m). Figure 22 8.2 Distribute and Secure the Tube Figure 23 8.2.1 Distribute the tubes in the order from the bottom of the unit to the top of the unit.
Page 9
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 Figure 24 8.3 Splicing and Fiber Management 8.3.1 Fusion splice each ribbon. Maximum number of fibers to be spliced is 192 fibers (Max. 16 splices:12f ribbon). Note: Refer to the splice manufacturer’s instructions for directions on fiber splicing. 8.3.2 Secure fiber protection sleeve in splice holder and coil fiber slack as shown in photo.
Page 10
Document: SP-F05-004 Date Issued: 07/17 Revision: 5 Appendix 1 Ring cut and remove outer cable sheath at the length of HSX (Splice box). Cut the slotted core as below. Edge of the cable sheath Length of removing cable sheath (depends on the size of SOFT) 0.59inch (15mm)