Equipment Summary
The "EQUIPMENT SUMMARY" screen will appear after
Accessories have been selected. This screen will give a summary of
all equipment automatically found or manually selected. If a wrong
selection was made, press left- -side button (BACK selection) to go
back to that particular screen and make changes. When everything
is OK, press right- -side button again to continue. (See Fig. 18.)
EQUIPMENT SUMMARY
FURNACE
58MVB0100-12
AC
24ANA136A003
FILTER
EAC
HUMIDIFIER
YES
UV LIGHTS
YES
ZONES
12345678
NO
YES
Fig. 18 - - Equipment Summary
The "SETUP COMPLETE! SAVE ALL SELECTIONS?" screen
will appear after Equipment Summary. To Save All Selections
press (YES) right- -side button. Pressing the left- -side button (NO
selection) will return to the Equipment Summary screen where
changes can be performed to any of the equipment selection
screens. After selecting YES, the initial power up sequence of the
new Evolution Zone Control is complete.
Static Pressure Check
STATIC
PRESSURE
CHECK
PLEASE WAIT
Fig. 19 - - Static Pressure Check
This screen will appear after Setup is exited. The system will open
all dampers and perform a static pressure check. This process will
take about 1- -1/2 minutes to complete. When completed, a screen
will appear displaying the static pressure (in inches) across the
equipment at the expected highest delivered airflow. If the blower
RPM is greater than 1200, then a warning will appear, but
equipment operation and the TrueSenset dirty filter detection
operation will not be affected.
NOTE: The static pressure check occurs only at initial installation,
or when INSTALL is run in the INSTALL/SERVICE menu.
Duct Assessment
The following screen will appear after STATIC PRESSURE screen
is exited. Press right- -side button to start Duct Assessment. Duct
Assessment will measure the relative size of the ductwork, up
and through the dampers. These measurements are used to control
ZONING
UI
RS
RS
RS
CONTINUE
A04084
SETUP
COMPLETE!
SAVE
ALL SELECTIONS/
NO
YES
A07024
EXTERNAL STATIC
PRESSURE
MEASURED:
0.72 INCHES
AT 1200 CFM
CONTINUE >
A05000
to
the correct amount of airflow in the zoned system. Status messages
will appear on the screen to indicate what the system is doing. The
process will take approximately one minute per zone. The duct
assessment will override a call for heat or cool.
A duct assessment will automatically occur each day at a user
selectable time. The factory default time is 1:00 p.m. but, may be
changed by entering the Zoning Setup menu. See Zoning Setup
section of this manual. The duct assessment will override a call for
heat or cool. The system will first open all zones and drive the
blower to 175 CFM/ton of cooling (or the minimum indoor unit's
airflow, whichever is greater). It will then take a static pressure
measurement. The system will then close all zones and open one
zone at a time, taking a static pressure measurement for each zone.
The system will then close all zones and take a pressure
measurement, getting a value for the duct leakage up to and
through the dampers. With these static pressure measurements, the
system will calculate the relative size of each zone as well as the
percent leakage through the dampers At the end of the process, the
display will show the relative size of each zone duct. See Fig. 20.
If the User Interface detects an error (damper not moving or
damper wired backwards), it will perform the duct assessment
again. If it still detects a damper problem, it will default the
measurements into equal sizes, with 10% leakage, and display the
zone number for the suspected zone damper.
DUCT ASSESSMENT
DUCT ASSESSMENT
ASSESSMENT ACTIVE
MEASURE DUCT
PLEASE WAIT
CAPACITY FOR EACH
OPENING ALL ZONES
ZONE.
AIRFLOW STABILIZING
4 MINUTES ARE REQUIRED
TO COMPLETE
PROGRESS
PRESS START TO BEGIN
QUIT
START
STOP
Fig. 20 - - Duct Assessment

QUICK START

For first time installers, Quick Start will allow a quick start up of
the Evolution Zone System before learning all the details of system
operation. However, for the best possible comfort and operation
refer to the Evolution Zone Control Owner's Manual.
Set Day, Time & Desired Humidity
1. Open the door of the Evolution Zone Control and press the
BASIC button.
2. Adjust the highlighted HOUR setting using the LEFT Up/
Down button.
3. Press SCROLL button (down) to highlight MINUTE.
4. Adjust the MINUTE setting using the LEFT Up/Down
button.
5. Press SCROLL button (down) to highlight DAY.
6. Adjust the current DAY setting using the LEFT Up/Down
button.
7. Press SCROLL button (down) to highlight HUMIDITY.
8. Press the red HEAT button to select heating humidity.
9. Adjust desired heating humidity level using either (+/- -) but-
ton.
10. Press the blue COOL button to select cooling humidity.
11. Adjust the desired cooling humidity level using ei-
ther(+/- -)button.
12. To exit press BASIC button or close door.
13. If changes are made, you will be asked to "SAVE
CHANGES? YES/NO."
7
DUCT ASSESSMENT
ZONE
CAPACITY
ZONE1
25
ZONE 2
20
ZONE 3
25
ZONE 4
20
DAMPER LEAKAGE 10
QUIT
START
A04085

Advertisement

Table of Contents
loading

Table of Contents