5. Transportation & installation

5.1. Transportation

Secure the unit with straps to prevent sliding or
tipping during transport.
Transport the unit only in a horizontal position.
Do not place the unit on the front where the
control panel is located, or on the top or bottom
where connections and outlets are located.
If the unit is moved when the temperature is near
or below 0°C (32°F), make sure it is fully emptied
of water to avoid damage.

5.2. Installation preparations

Read all the included information for safety rea-
sons before installing the equipment.
Follow the applicable laws and regulations at the
time of purchase, in addition to this manual.
Installation must always be in accordence with
local legistration.
Consider leaving at least 1m free space around
the unit for easier maintenance.
Rinse the pipeline thoroughly before connecting
the unit.

5.3. Mounting Instructions

For safe mounting, note the following:
Only install the unit in a frost-free area.
Remove the cover before mounting the unit on
the wall.
Use a stable brick or concrete wall, or a separate
frame anchored to the floor.
Refer to the installation drawing for recommend-
ed installation height. The height can be adjusted
for the operator's reach to valves and display.
Mount the bracket on a stable brick or concrete
wall using the enclosed screws and rawplugs.
If the wall is not made of bricks or concrete, en-
sure it can support the weight of the unit.
Hang the unit on the bracket and secure it with
two screws through designated holes.
Secure the unit in the top by two screws through
the designated holes. Refer to installation draw-
ings in section 12.2 and 12.3.
Mount the hose holder and user pack holder if
any.

5.4. Electrical installation

Refer to section 11 for electrical diagrams and rat-
ings.

5.4.1. Power supply

Connection instruction is mounted on the cables.
The phase order is subordinated.

5.4.2. Earth leakage circuit breaker (ELCB).

Use an earth leakage circuit breaker (ELCB), also
known as a residual current device (RCD) or a
residual current circuit breaker (RCCB), in a system
that includes a variable speed drive connected to 3
phase 400V.
The trip level of the ELCB must be 300mA.
Note that the 30mA used in households can malfunction
due to earth leakage.

5.4.3. Service switch

The unit must always be connected to the main sup-
ply through a separate service switch.
MH42 / MP42
Voltage:
3/PE 380-528
Vac
Fre-
50/60 Hz
quenz:
48-62
Motor
5.5 kW
load:
Nominal
14.2 A
current:
Fuse:
20 A
L1, L2,
4 x 2.5 mm²
4 x 2.5 mm²
L3, PE
BH4 / BP4
BH7
3/PE 380-
3/PE 380-
528
528
Vac
Vac
50/60 Hz
50/60 Hz
48-62
48-62
5.5 kW
10 kW
14.2 A
27 A
20 A
32 A
4 x 6.0 mm²
36