Samsung AM TN4 KH Series Installation Manual page 36

Table of Contents

Advertisement

Installation Procedure
Performing final check and trial operation
To complete the installation, perform the following checks and tests to ensure that the air conditioner operates
correctly.
1 Check the followings.
• Strength of the installation site
• Tightness of pipe connection to detect a gas leak
• Electric wiring connections
• Heat-resistant insulation of the pipe
• Drainage
• Earth conductor connection
• Correct operation (follow the steps below)
After finishing the installation of the air conditioner, you should explain the following to the user. Refer to appropriate
pages in the User's Manual.
1 How to start and stop the air conditioner
2 How to select the modes and functions
3 How to adjust the temperature and fan speed
4 How to adjust the airflow direction
5 How to set the timers
6 How to clean and replace the filters
NOTE
• When you complete the installation successfully, hand over the User's Manual and this Installation Manual to the
user for storage in a handy and safe place.
36
English

Advertisement

Table of Contents
loading

Table of Contents