13.0
Changing Components
13.3
Flowswitch
(Fig. 47)
1. Drain the boiler (see Section 13.1 paragraph 2 & 3).
2. Remove the two screws on the support bracket.
3. Remove the clip securing the flow pipe to the
Support Bracket
flowswitch.
4. Disconnect the inline electrical connection.
5. Pull pipe away from flowswitch.
6. Remove the two screws securing the flowswitch to
the boiler.
7. Remove the flowswitch.
Flow Switch
8. Fit the new flowswitch and reassemble in reverse
Flow Pipe
order.
9. Recommission the boiler and check the inhibitor
concentration (see Section 6.2 and 10.1).
Fig. 47
Clip
36
© Baxi Heating UK Ltd 2006