PLACING WATER SYSTEM INTO OPERATION

1. Flush water lines
NOTE: After inlet, outlet, brine and drain connections are completed, but before restoring water to house:
Open the inlet ball valve.
Close the inlet boiler drain.
Close the outlet ball valve.
Turn the bypass handles to the bypass position as shown in
to the right
Open the outlet boiler drain on the outlet side of the system.
Slowly turn on the water supply to the house and flush the lines into
a bucket or garden hose to purge color, cement, sealants or solder
residue.
Once the lines are clear close the outlet boiler drain.
Check all new connections for leaks.
With the water supply to the house still on and the bypass in bypass
position proceed to the next section.
2. Plug in, initialize, and set time on the water system control
Plug the control into power outlet, the display will flash through diagnostic screens, the motor will energize, and
index the piston to the service cycle..
The display will flash "TIME OF DAY". Set Time of Day:
STEP 1U
STEP 2U
STEP 3U
RETURN TO
NORMAL MODE
STEP 1U – Press CLOCK.
STEP 2U - Current Time (hour): Set the hour of the day using ▼or ▲. AM/PM toggles
after 12. Press NEXT to go to Step 3U.
STEP 3U - Current Time (minutes): Set the minutes of the day using ▼ or ▲. Press
NEXT to exit Set Time of Day. Press REGEN to return to previous step.
SUPPLY
WATER
Figure 22
SUPPLY
WATER
EXITS
ENTERS
Figure 22