Installation Guidelines
For All Power Optimizers, except for the P860, P960 and M1600
For P860, P960 and M1600 Power Optimizer
Figure 3: Clearance for heat dissipation around the Power Optimizer
Equipment grounding tightening torques: 4-6 AWG: 45 lb-in, 8 AWG: 40 lb-in, 10-14
AWG: 35 lb-in.
When installing PV modules in a confined space such as Building-integrated
photovoltaic (BIPV) modules, ventilation measures may be required to ensure that
the Power Optimizers are not exceeding the maximum temperatures stated in their
specifications.