Advertisement

M500-605-100-M01 Rev 1.00
WORK INSTRUCTION
Sealing Methods – C510, C520 and C527

Sealing with calibration seal stickers

Equipment required.
• Destructible stickers
• Setup switch cover
• Load cell connection cover (M5010)
Method
1. Place the setup switch cover in position so that it covers the setup switch and 2
closure screws.
2. Place a sticker over the centre of the setup switch cover and onto the side of the
enclosure as shown in Figure 1.
Page 1
M500-605-100-M01

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the C510 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Rinstrum C510

  • Page 1 M500-605-100-M01 Rev 1.00 WORK INSTRUCTION Sealing Methods – C510, C520 and C527 Sealing with calibration seal stickers Equipment required. • Destructible stickers • Setup switch cover • Load cell connection cover (M5010) Method 1. Place the setup switch cover in position so that it covers the setup switch and 2 closure screws.
  • Page 2 M500-605-100-M01 Rev 1.00 WORK INSTRUCTION Figure 1: Setup Switch and pluggable screw terminal load cell connection sealing with a sticker. 3. Either • Place the load cell connector adaptor cover over the load cell connector adaptor and place a sticker across the load cell connector adaptor cover as shown in Figure 1.
  • Page 3 M500-605-100-M01 Rev 1.00 WORK INSTRUCTION Figure 2: Sealing DB9 loadcell connection. Sealing with wire and Lead seals The Setup switch cover and pluggable screw terminal load cell connection can also be secured with wire and Lead seals if required. This will also seal access to two of the enclosure closure screws.
  • Page 4 M500-605-100-M01 Rev 1.00 WORK INSTRUCTION Figure 3: Wire seal loop locations Page 4 M500-605-100-M01...

This manual is also suitable for:

C520C527C530

Table of Contents