Page 1
INSTALLATION AND MAINTENANCE INSTRUCTIONS FlamQuench II™ VENTING WITH FLAME AND PARTICLE RETENTION - PASSIVE EXPLOSION PROTECTION Doc. 8.8520.00.5 Rev. April, 2019 SOLUTIONS Fire Protection Explosion Protection Overpressure Protection Pressure Activation...
Page 2
Fike products. Do not use any Fike products for any application for which it is not intended. Fike shall not be in any way liable for any damages or losses incurred by you or third parties arising from the use of any Fike product for which the product is not intended by Fike.
Page 3
REVISION HISTORY : ............................June, 2017 RIGINAL ELEASE EVISION ESCRIPTION OF HANGE EVISION 4 / Change 5m hearing protection to 10 X D hearing protection January 2018 Doc. P/N 8.8520.00.5 PAGE / 1 Rev. April, 2019...
Tools Needed for Refurbishment (not included as part of kit) ................7 SCHEDULED MAINTENANCE ............................8 6.1. Every Three (3) Months ............................. 8 MAINTENANCE AFTER EACH FLAMQUENCH II ACTIVATION ..................8 EXPLOSION VENT REQUIREMENTS ..........................8 PAGE / 2 Doc. P/N 8.8520.00.5...
Fike FlamQuench II. Fike Corporation has designed and manufactures the FlamQuench II in two versions: an imperial size unit specified according to NA standards, available in size 8” through 40”; and a metric version specified and built for the CE market, available in size DN200 through DN1000.
The FQ devices reduce the noise level compared to an open vent by ~10 dB(A). Fike recommends that the user provide appropriate hearing protection for workers who may be in the vicinity (within 10 x D) of the vent device. Local regulations may prevail.
8. Connect Burst Indicator. (See Installation Instructions on connecting BI) Note: Cables attached to lifting rings can be used to help support the FlamQuench II. Do not attempt to support the FlamQuench II using any other method other than the lift rings 2.6.
4. SUPPORT CONSIDERATIONS The FlamQuench II should be supported to prevent damage to the vessel it is protecting. If the vessel is sufficiently sturdy, the flange connection may be used to support the FlamQuench II. Weight and angle must be considered when evaluating vessel strength for mounting.
36” (DN900) E85-039-36 91002720-S 40” (DN1000) E85-039-40 91002820-S Note 1: DN800 and DN900 FlamQuench II both use the same filter elements. 5.4. Tools Needed for Refurbishment (not included as part of kit) Doc. P/N 8.8520.00.5 PAGE / 7 Rev. April, 2019...
7. MAINTENANCE AFTER EACH FLAMQUENCH II ACTIVATION Replacement is required after every activation. This includes replacing filters and hardware (See Section 5). 8. EXPLOSION VENT REQUIREMENTS The following round Explosion Vents have been approved for use in conjunction with the FlamQuench II. HI-CV ...
Page 20
CONTACT US Fike Europe Toekomstlaan 52 2200 Herentals, België Tel: +32 14 210031 www.Fike.com For a list of contact information for Fike offices around the world, visit the Global Locations section of Fike.com...
Need help?
Do you have a question about the FlamQuench II and is the answer not in the manual?
Questions and answers