Environmental protection tank

Advertisement

Quick Links

Installation Instructions
JATCO Environmental Protection Tank
J-5000 SM-P
*INSTRUMENTATION GAS IS MANDATORY FOR SUPPLY GAS*
The JATCO Environmental Tank must be installed at a level which will allow the waste liquids to be
disposed of to gravity flow into the tank.
IMPORTANT: The top of the tank must be below the level of waste liquids to be received.
Inlet and the outlet check valves are both teed from the same port near the bottom of the tank (end opposite
the sight glass). When facing this end, the inlet check valve is on the left (A) and the outlet check valve
is on the right (B).
The discharge should be piped directly to the storage tank that is to receive the waste liquid. The discharge
may be teed into an existing flow line, provided that a high-pressure check valve (1000 psi) is installed to
prevent high pressure from returning to the discharge check valve on the JATCO tank.
The tank supply gas must have adequate
volume
and pressure. For best operation use 1" pipe for the tank
supply gas plumed as close to the tank as possible. Then reduce down to the tubing connection (C) on the
JATCO tank.
Supply gas pressure minimum (40 psi) is connected to the bottom inlet of the level control valve (C)
this gas pressure must not exceed (75 psi) for normal operation. No pressure regulator is provided.
Gauge cock knobs are removed for shipping.
Depressing the manual dump plunger allows the operator to check function of the float and level control
valve. When the plunger is depressed, the tank will cycle once and return to the automatic operation.
The plunger button should be returned to the extended position.
3-way pilot valve (G) is vented thru ¼" NPT port (H).
Liquid levels in the JATCO tank may be observed in the sight glass furnished as standard
equipment.
th
244 N.W. 111
St.
Oklahoma City, Oklahoma 73114 •
405/755-4100 • 405/755-4101 Fax

Advertisement

loading

Summary of Contents for Jatco J-5000 SM-P

  • Page 1 J-5000 SM-P *INSTRUMENTATION GAS IS MANDATORY FOR SUPPLY GAS* The JATCO Environmental Tank must be installed at a level which will allow the waste liquids to be disposed of to gravity flow into the tank. IMPORTANT: The top of the tank must be below the level of waste liquids to be received.
  • Page 2 Service Guide JATCO Environmental Tanks J-5000 SM-P *INSTRUMENTATION GAS IS MANDATORY FOR SUPPLY GAS* Listed below are a series of steps to follow if the JATCO tank fails to dump properly. volume The tank supply gas must have adequate and pressure. For best operation use 1”...
  • Page 3 J-5000 SM-P A. Inlet Check Valve 1" NPT JM5005 B. Discharge Check Valve 1" NPT JM5005 17” C. Supply Gas Inlet ½" Compression (40-75 psi) D. Liquid Level Control Valve JM5011 SM-P 9 ¼” E. Pressure Relief Valve JM5002-100 29”...
  • Page 4 JATCO Inc. J-5000cx & J-5000 SM-P Tank Parts J-5000 SM-P J-5000cx 9 & 10 No. Item# Description JM5001X 3-Way Micro Valve w/Mounting Plate JM5002 -100 ¼" SS Pressure Relief Valve 100 PSI JM5002 -200 ¼" SS Pressure Relief Valve 200 PSI ⅜"...
  • Page 5: Warranty

    The sole liability and exclusive remedy is limited to the repair or replacement, at the option of JATCO, Inc., of the product, or any parts thereof, which upon examination by JATCO, Inc., disclose to its satisfaction defects due to faulty material or poor workmanship, and which defects are reported to JATCO, Inc., in writing, during the warranty period.
  • Page 6 JATCO, Inc. to notify any person of such revisions or changes. It shall be the user’s responsibility to determine whether any changes or revisions to this manual have been made.