Skov DA 150B Technical User Manual

Skov DA 150B Technical User Manual

Pad cooling

Advertisement

Quick Links

DA 150B Pad Cooling
Technical User Guide
2022.05.05 • 604164

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the DA 150B and is the answer not in the manual?

Questions and answers

Summary of Contents for Skov DA 150B

  • Page 1 DA 150B Pad Cooling Technical User Guide 2022.05.05 • 604164...
  • Page 3 Product and Documentation Changes SKOV A/S reserves the right to change this manual and the product described herein without further notice. In case of doubt, please contact SKOV A/S. Date of change appears from the front and the back page.
  • Page 4: Table Of Contents

    Pad ................................ 14 1.1.9 DA 150B Pump ............................14 1.1.10 DA 150B / DA 100 B Pad cooling check valve kit ................. 14 1.1.11 DA 150B Glue Kit - max. 12 m ......................15 General Information ....................16 Recommended Tools ......................16 Safety Guidelines - Intended Use ..................
  • Page 5 Technical User Guide Maintenance Routines ...................... 39 Technical Data ......................43 Load on the Bracket ......................43 Water Quality ........................43 DA 150B Pad Cooling...
  • Page 6: Product Description

    Overview of DA 150B Pad Cooling System The “DA 150B pad cool basic 6 m” or “DA 150B pad cool basic 3 m” are complete 6 m or 3 m pad cooling systems and consist of a supply unit, a middle element with end kit and a check valve.
  • Page 7: 150B Pad Cooling, Supply Unit

    Technical User Guide 1.1.1 DA 150B Pad Cooling, Supply Unit DA 150B pad cooling, supply unit is included in the “DA 150B pad cool basic 6 m” and “DA 150B pad cool basic 3m”. The following part numbers are available: •...
  • Page 8: 150B Pad Cooling, Middle/End Kit 6 M

    Technical User Guide 1.1.2 DA 150B Pad Cooling, Middle/End Kit 6 m DA 150B pad cooling, middle/end kit is included in the “DA 150B pad cooling, basic 6 m”. The following part number is available: • 437775 DA 150B pad cool middle/end kit 6m 437775 DA 150B pad cool middle/end kit 6m Pos.
  • Page 9: 150B Pad Cooling, Middle/End Kit 3 M

    Technical User Guide 1.1.3 DA 150B Pad Cooling, Middle/End Kit 3 m DA 150B pad cooling, middle/end kit is included in the “DA 150B pad cooling, basic 3 m”. The following part number is available: • 437780 DA 150B pad cool middle/end kit 3m 437780 DA 150B pad cool middle/end kit 3m Pos.
  • Page 10: 150B Pad Cooling, Extension 3M

    DA 150B Pad Cooling, Extension 3m DA 150B pad cooling, extension 3 m is used if a pad cooling system longer than 6 meter is required. The total length of a pad cooling system can be up to 24 metres.
  • Page 11: 150B Pad Cooling, Extension 2X3M

    DA 150B Pad Cooling, Extension 2x3m DA 150B pad cooling, extension 2x3 m is used if a pad cooling system longer than 6 meter is required. The total length of a pad cooling system can be up to 24 metres.
  • Page 12: 150B Pad Cooling 3 M Corner Connection

    DA 150B Pad Cooling 3 m Corner Connection DA 150B pad cooling 3 m corner connection is used if a pad cooling system must be mounted around a corner of the building. With the corner connection, it is also possible to have a distance between the basic system and the corner connection.
  • Page 13: 150B Pad Cooling Corner Connection Kit

    1.1.7 DA 150B Pad Cooling Corner Connection Kit DA 150B pad cooling corner connection kit is used for connecting the DA 150B pad cooling 3 m corner connection and extensions up to 12 m after a corner. Maximum length from the corner is 2.5 m in both directions.
  • Page 14: Pad

    DA 150B pump 1x230V 60Hz 437375 DA 150B pump 1x230V 50Hz 350W 437374 DA 150B pump 3x230/400V 60Hz 1.1.10 DA 150B / DA 100 B Pad cooling check valve kit Pad cooling check valve kit Item no. Description 437947 DA 100B/150B check valve kit...
  • Page 15: 150B Glue Kit - Max. 12 M

    Technical User Guide 1.1.11 DA 150B Glue Kit - max. 12 m 437584 DA 150B Glue Kit - max. 12 m Pos. Number Item no. Description 530187 PVC-U glue Tangit 500g 530181 PVC-U cleaning fluid Tangit 1000ml 530003 Brush 530186 PVC-U glue Tangit 125 g paste tube Safety advice –...
  • Page 16: General Information

    Technical User Guide 2 General Information 2.1 Recommended Tools Below is a list of tools required for installation of your SKOV pad cooling system. Item. Description Electrical Jig saw Blades for cutting steel Blades for cutting wood Angle Grinder With grinder disk for Steel/Iron...
  • Page 17 Technical User Guide Item. Description Chalk string Hammer Screwdriver set Pliers Wrench Vise-Grip Knife/Cutter Marking Pencil Spanner/Wrench set in Metric measurement Adjustable spanner 10” Ratchet Tie Down 20meters Hole Saw 76 mm Market Pen DA 150B Pad Cooling...
  • Page 18: Safety Guidelines - Intended Use

    The installation of a supply isolator is required for each motor and power supply, so maintenance of electrical equipment can be carried out in a dead environment. Supply isolator is not supplied by SKOV A/S. Mount the pump according to the supplier instruction manual.
  • Page 19: Circuit Diagram1X230 V

    Technical User Guide 2.3.1 Circuit Diagram1x230 V 2.3.2 Circuit Diagram 3x230 V DA 150B Pad Cooling...
  • Page 20: Mounting Guide

    Important: The frame must be smooth, in level and able to hold the weight of the pad cooling system, see section 5.1 and 3.15. = 170 mm = 320 mm Figure 2: Total height – wall-mounted DA 150B Pad Cooling...
  • Page 21: Total Height Of Pad Cooling System, Floor

    It is important that the vertical sides are perpendicular to the horizontal sides. • Use a square to make the sides perpendicular. • Use a chalk line as guide when cutting the opening. Figure 4: Wall opening DA 150B Pad Cooling...
  • Page 22: Bracket For Water Gutter

    Max. 750 mm between Bracket for brackets for pad support supply unit 3.4.2 Uneven number of extension sets Dimensions in mm. Center of the hole Max. 750 mm between Bracket for brackets for pad support supply unit DA 150B Pad Cooling...
  • Page 23: Water Gutter

    Mount the supply unit, see section 3.4. Figure 7: Water gutter with supply unit Mount the end cover on the water gutter. Figure 8: Water gutter end cover Now the water gutter is ready for connection with glue, see section 3.10. DA 150B Pad Cooling...
  • Page 24: Top Bracket

    B = Measure from the lower edge of the top bracket to the top of the pad support. 1540 mm 1840 mm 2010 mm Figure 9: Top bracket DA 150B Pad Cooling...
  • Page 25: Water Distribution Pipe

    If more than 100 mm between the holes. Drill a ø 4 mm hole in the T-glue coupler. Air flow Connect the water distribution pipes with pipe connectors and clamps for pipe connector. Remember to tighten the clamps. Figure 10: Water distribution pipe DA 150B Pad Cooling...
  • Page 26: Deflector

    Use a 3” (Ø76) hollow drill for the final hole. Burr the drilled hole before the deflector is being clicked into place. Click the deflector into place. Use deflector coupler to connect deflectors Figure 11: Deflector DA 150B Pad Cooling...
  • Page 27: Inner Pad Guide

    Cut and stick together the piping system from the pump to the supply unit and the piping to the drain. Consider the arrangement of the construction units. Tighten all unions at supply unit Figure 13: Piping DA 150B Pad Cooling...
  • Page 28: Supply Unit

    Mount the 2 check valve brass on the transition " piece 2 for supply unit on the inside of the supply " unit tank. Tighten the parts together. Check that the float valve can is adjustable. DA 150B Pad Cooling...
  • Page 29: Water Distribution

    3. At the centre, the pipe is connected to the T-glue coupler. 4. Bleed off valve. Figure 15: Water distribution Connection of water should take place later so the system is not filled inadvertently. DA 150B Pad Cooling...
  • Page 30: Prior Start Up

    The maximum water level should not exceed 20 cm. Ensure that the float valve can switch according to its function. Generally, water should not escape from the overflow holes. The holes only serve as an overflow for strong precipitation. DA 150B Pad Cooling...
  • Page 31: Glue Instruction

    Technical User Guide 3.10 Glue Instruction 3.10.1 Glued Connections SKOV recommends "Tangit" adhesive for glued connections. Many connection elements in this product are designed as glued connections. Please observe the following manufacturer instructions in order to ensure secure connections. Figure 16: Glue connections The pipe must be cut at a right angle and burred.
  • Page 32: Safety Advice - Tangit Pvc-U/C

    In case of ingestion - rinse mouth with plenty of water and give 1 – 2 glasses of water – DO NOT INDUCE VOMITING – seek medical advice. Fire fighting In case of fire – use carbon dioxide, foam, powder, water spray Emergency telephone Safety sheet +49(0)211-797-3350 (24hour) ua-productsafety.de@henkel.com DA 150B Pad Cooling...
  • Page 33: Glue Water Gutter And Pipes

    Tangit glue. Please consider the general references for handling Tangit in the Assembling and Operating Instructions (In particular the processing time: 4 min. at 20°C). Spread immediately the Tangit glue on the glue surface both inside and outside of the water gutter or pipe. DA 150B Pad Cooling...
  • Page 34 Please consider the drying times in the Assembling and Operating Instructions! When gluing meters of water gutter together with joint for water gutter. Use a ratchet tie down. Use ratchet tie down to join water gutter together. DA 150B Pad Cooling...
  • Page 35: Covers And

    Remove 20 mm at the bottom of outer protuberance prior to mounting of the pad end cover. Make a cut in the bottom of the end cover 10 x 20 mm Then fit the end cover to the wall. DA 150B Pad Cooling...
  • Page 36: Bleed Off Valve

    Glue the bleed off valve to the end of the pipe. Mount the clamp ¾” together with the black tube ¾”, so the water is lead to the drainage. Figure 18: Mounting of ball valve for bleed off DA 150B Pad Cooling...
  • Page 37: Pad

    Open Pad guides are assembled by means of a pad guide coupler. Remember to lock the pad guide coupler after being mounted. Closed Figure 20: Mounting of outer pad guide DA 150B Pad Cooling...
  • Page 38: Pointing Sealing Edge

    3.15.1 Flat and smooth wall Sealing edge Apply a sealing edge between the pad and the frame made of a water-resistant material (not supplied by SKOV) in that way the air can only enter through the pads. 3.15.2 Uneven and not smooth wall...
  • Page 39: Maintenance Instructions

    Adjust the opening of the ball valve to 12 l/min when the water distribution is on. Maintenance Routines Clean the filter in the pump at least once a week, more often if foreign bodies ingress the water system. DA 150B Pad Cooling...
  • Page 40 1. Click the deflector out of its position 2. Clean any clogged up holes with a wire until adequate water flows from each hole. 3. Clean the pipes outside for dirt and burrs. DA 150B Pad Cooling...
  • Page 41 Clean any clogged up holes with a wire until adequate water flows from each hole. NOTE DO NOT FLOW EXCESSIVE WATER ON THE PAD DA 150B Pad Cooling...
  • Page 42 See picture. It will be possible for customers to deliver SKOV products to local collection sites/recycling stations in accordance with local instructions. The recycling station will then arrange for further transport to a certified plant with view to recycling, reclaim and reuse.
  • Page 43 6m pad cool supply pad cool basic 3m pad cool basic 6m 1x230V 50Hz 1x230V 60Hz 1x230V 50Hz 3X230/400V60Hz Electric DA 150B pump 437371 437370 437375 437374 Supply voltage [V] 1x230 (± 10 %) 1x230 (± 10 %) 1x230 (±...
  • Page 44 SKOV A/S • Hedelund 4 • Glyngøre • DK-7870 Roslev Tel. +45 72 17 55 55 • Fax +45 72 17 59 59 • www.skov.com • E-mail: skov@skov.dk...

Table of Contents

Save PDF