WALL MOUNTED BUBBLE WALL (BWWMP)
Installation and Operation Instruction
Use only distilled water- 14 Litres required
Unpack all components and check contents against inventory list below.
Advise supplier immediately if parts are missing.
Brief Description for Components
No
Name of parts
Function description
1
One (1)-Metal Frame
Brushed Stainless Steel Frame.
2
One (1)-Acrylic Panel
Acrylic panel is used to hold water, display of dancing
illuminated bubbles.
3
One (1)-Hanging bar
A board to fix screw on wall for hanging bubble wall.
4
One (1)-Remote Control
To control the color and the light of LED LIGHT.
5
One (1) -Water-Pump
Produce Air & generate bubbles.
6
One (1)-Transformer
Supply Power.
7
One (1)-Metal Screw
Screw used to fix the Hanging bar on wall.
8
One (1)-Controller
Equipment designed to receive remote control order.
9
One (1)-PVC Water Pipe
PVC Water Pipe is tool for water injection in and draining
water off from Acrylic Panel.
10
Two (2) - Blue Nozzles
Outlet of gas that connects with the Air-pipe in pump.
11
One (1)- Taper sleeve
The raw plugs
Components Photos
Specific Installation steps as follows:
IMPORTANT: 2 peoples are required to safely assemble and install this unit.
Do not attempt to assemble on your own.
Step 1
Fix the hanging metal with screw on your suitable wall.
Step 2
Connect the transformer cord to the controller cord which is on the bottom side of acrylic
panel.
Step3
Carefully add water through the top of panel until reaching max level mark.
Hang the bubble wall with two people on the hanging metal on the wall.
Step4
Plug transformer into mains power supply.
Caution & Maintenance
The controller should be out of the base when in use.
Ensure the blue nozzles are inserted properly in the acrylic panel and connected with the
Air-pipe from the pump in case of any water leak.
Ensure the air-pipe is straight to avoid any bubbles coming out.
The bubble wall will continue to lose water due to evaporation after a few months of
operating, which is dependent on a many variables such as climate, humidity,
temperature, etc. it may be require to refill water.
It is recommended to clean the inside of your bubble wall every three month with mild
lotion and a soft towel.
SAFETY INSTRUCTIONS
FAILURE TO FOLLOW THESE SAFETY INSTRUCTIONS MAY RESULT IN SERIOUS
INJURY OR PROPERTY DAMAGE. Proper and complete assembly and good use are
essential for proper operation and to reduction the risk of injury. 2 people are required for
assembly. • If technical assistance is required, contact the vendor.
Most injuries are caused by misuse and/or failure to follow instructions.
Do not attempt to move the assembled unit once it's filled with water. Turn Power off this unit
before removing.
MADE IN CHINA

Advertisement

loading
Need help?

Need help?

Do you have a question about the BWWMP and is the answer not in the manual?

Questions and answers

Summary of Contents for Playlearn BWWMP

  • Page 1 Specific Installation steps as follows: WALL MOUNTED BUBBLE WALL (BWWMP) Installation and Operation Instruction IMPORTANT: 2 peoples are required to safely assemble and install this unit. Use only distilled water- 14 Litres required Do not attempt to assemble on your own.
  • Page 2 Press the key of "ON “to check the led light. If you need any advice or help with set up, please contact; Playlearn Ltd by email - HELP@PLAY-LEARN.CO.UK 3. Why is not there air expel from outlet of gas?