Installation of the AKR 30/50 Remote Racker
Mounting Bracket Kit – AKR3050EGBRMOD
When looking at the front of the breaker, locate
the (2) mounting holes that are already
punched in the frame on the left side of the
escutcheon.
They are located behind the
nameplate on the breaker.
Install the mounting bracket that came with
your kit. Align the (2) holes on top of the bracket
with the (2) holes on the frame. Install the (2) ¼-
Nameplate
Mounting Bracket
AKR 30/50 Mounting Bracket Installation
Remote Racking Operator for AKR Breakers
20 flat washers, lock washers and bolts through
the frame and into the bracket. Torque the
bolts to 7 – 10 ft.-lbs. Do not over torque. Make
sure that the flat portion of the bracket with the
key way is facing outwards. See picture below.
After the bracket has been mounted, the
breaker is ready to be installed into the cubicle.
The existing racking screw mechanism needs to
be inspected for excessive wear and be
properly lubricated.