EDMS NO. REV. VALIDITY 1867100 RELEASED REFERENCE TOF-TAR-PRD-0001 CERN CH1211 Geneva 23 Switzerland Date: 2019-04-11 nTOF – Target 2 Removal Handling Tasks CUMENT TYPE] (Sequence of Operations) Abstract – This document outlines the tasks needed to remove n_TOF Target 2 in order to allow its replacement with Target 3.
Page 2
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 2 of 93 HISTORY OF CHANGES REV. NO. DATE PAGES DESCRIPTIONS OF THE CHANGES 2017-08-04 First draft with illustrations based on discussions between O.Aberle, K.Kershaw and nTOF EAR2 beam line installation procedure document.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 3 of 93 TABLE OF CONTENTS Introduction ..................................... 6 Scope ......................................7 Tasks ......................................7 10. Preparation of area (EAR2 & Technical Gallery) ..........................8 20. Break vacuum .......................................9 30. Disconnect filter box and permanent magnet vacuum tubes ....................10 40.
Page 4
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 4 of 93 300. Remove support frame for vacuum chamber 1 .......................... 41 310. Remove square shielding..................................42 320. Remove support for square shielding ............................. 43 330. Drain upper section of pipes from the cooling station ......................44 331.
Page 5
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 5 of 93 610. Cut the pipes and place them into containers ..........................82 620. Pipe assembly removal, cooling station side ..........................83 630. Pipe assembly removal, pit side ................................ 84 640.
Important CATIA models: ST0332721_01 – n_TOF EAR2 Area ST0083420_01 – Target 2 Important drawings: CERN Drawing Number: TOFEAR2_0154 A schedule for this tasks has been drafted. At the time of writing, it is under discussion (EDMS 2066754).
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 7 of 93 2. Scope This document covers the handling tasks needed for the removal of the equipment within the vertical beam pipe and then the removal and dismantling of the old Target 2, so that the new target 3 can be installed.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 8 of 93 Name of task 10. Preparation of area (EAR2 & Technical Gallery) Exposed people Local dose rate 0.1 µSv/hr Workforce 5 people Time needed 2 weeks Calculated dose EAR2 and Responsible EN-EA Detector...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 9 of 93 Name of task 20. Break vacuum Exposed people Local dose rate 0.1 µSv/hr Workforce 1 person Time needed Calculated dose EAR2 and Detector Responsible EN-EA Involved EN-EA/ HE-RP/ TE-VSC Comments: The valves that allow the venting can be operated from EAR2.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 10 of 93 Name of task 30. Disconnect filter box and permanent magnet vacuum tubes Exposed people Local dose rate 0.5 µSv/hr Workforce 2 people Time needed Calculated dose Responsible EN-EA Involved EN-EA/ TE-VSC Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 11 of 93 Name of task 40. Remove magnet Exposed people Local dose rate 0.5 µSv/hr Workforce 5 people Time needed 1.5 day Calculated dose Responsible EN-EA Involved TE-MSC/ EN-HE/ EN-EA Comments: To be stored in the ISR8 Storage Area.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 12 of 93 Name of task 50. Remove filter box Exposed people Local dose rate 0.5 µSv/hr Workforce 4 people Time needed 0.5 days Calculated dose Responsible EN-EA Involved EN-HE/ EN-EA Comments: To be stored in the ISR8 Storage Area.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 13 of 93 Name of task 60. Fit cover plate to vacuum chamber 1 Exposed people Local dose rate 0.5 µSv/hr Workforce 2 people Time needed 15 minutes Calculated dose Responsible EN-EA Involved EN-EA...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 14 of 93 Name of task 70. Remove rails and aluminium ventilation sealing plate Exposed people Local dose rate 1 µSv/hr Workforce 2 people Time needed Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: All the rails should be removed in order to gain...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 16 of 93 Name of task 90. Remove upper bellow Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: The upper bellow needs to be removed to allow a flat plate to be placed over the pit.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 17 of 93 Name of task 100. Install supporting plate over pit Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: This cover will needed to support vehicles, ladders,...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 18 of 93 Name of task 110. Remove connecting pipe Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 0.5 days Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE Comments: The gazelle will be needed.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 19 of 93 Name of task 120. Remove vacuum chamber upper parts Upper Vacuum Chamber Parts Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 0.5 days Calculated dose Responsible EN-STI Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 20 of 93 Name of task 130. Remove pillar structure and detector assembly Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 0.5 days Calculated dose Responsible EN-STI Involved EN-STI/ EN-HE/ HSE-RP Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 21 of 93 Name of task 140. Remove cover, lead, vacuum valve, transition flange, Al vacuum chamber Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 0.5 days Calculated dose Responsible EN-STI...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 22 of 93 Name of task 150. Remove borated polyethylene elements and B4C Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-STI Involved EN-STI / EN-HE/ HSE-RP Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 23 of 93 Name of task 160. Remove collimator-2 Exposed people Local dose rate 0.5 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-STI Involved EN-STI/ EN-HE/ HSE-RP Comments: Collimator2 is 2m long steel.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 24 of 93 Name of task 170. Remove steel balls Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 1 day Calculated dose Responsible EN-EA Involved EN-EA/ EN-STI/ EN-HE/ HSE-RP Comments: Should drain from two valves at the bottom (in...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 25 of 93 Name of task 180. Remove big Big collimator vessel collimator vessel and vacuum chamber 4 Exposed people Local dose rate 0.1 µSv/hr Workforce 4 people Time needed 4 hours Calculated dose Responsible EN-EA...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 26 of 93 Name of task 190. Remove the flange support and the sliding pads Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 27 of 93 Name of task 200. Remove concrete ring Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 1 day Calculated dose 1500mm Responsible EN-EA Involved EN-EA/ EN-HE/ EN-STI/ HSE-RP Comments: Installed via building 380 with the crane.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 28 of 93 Name of task 210. Remove support for steel sphere system Exposed people Local dose rate 0.1 µSv/hr Workforce 4 people Time needed 4 hours Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 29 of 93 Name of task 220. Prepare area for Target #2 removal (items below the gallery) Exposed people Local dose rate Workforce Time needed Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: Checking/Cleaning Nothing remaining to be done above...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 30 of 93 Name of task 230. Remove supporting cover over Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: This is the same cover that was installed in task 100.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 31 of 93 Name of task 240. Remove inner collimator from vacuum chamber Exposed people Local dose rate 1 µSv/hr 2.21m Workforce 2 people 410 kg Time needed 30 minutes Calculated dose Responsible EN-EA Involved...
Page 32
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 32 of 93 Dose rates: 1 µSv/hr Dose rates just above the bottom: 100 µSv/hr @ 10 cm Dose rates at the bottom: 200 µSv/hr @ 10 cm...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 33 of 93 Name of task 250. Remove remaining parts over long vacuum chamber Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 34 of 93 Name of task 251. Install cover over vacuum chamber Exposed people Local dose rate 10 µSv/hr Workforce Time needed Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: A cover needs to be installed over the vacuum chamber, to stop things accidentally falling in it.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 35 of 93 Name of task 252. Remove steel shielding from around vacuum chamber Exposed people Local dose rate 10 µSv/hr Workforce 4 people Time needed 2 hours Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 36 of 93 Name of task 260. Remove long vacuum chamber Exposed people Local dose rate 10 µSv/hr Workforce Time needed 2 days Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP/TE- VSC/EN-STI Comments: Alignment distances from walls written in past by...
Page 37
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 37 of 93 Dose rates: 1 µSv/hr First cut (chamber vertically in the pit) Second cut (chamber vertically in the pit) Third cut (chamber lying horizontally in EAR2) Dose rates: 2 mSv/hr @ 10 cm...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 38 of 93 Name of task 270. Install monorail above shaft Exposed people Local dose rate 1 µSv/hr Workforce 4 people Time needed 0.5 day for installation + 2 hours for load test Calculated dose Responsible EN-HE...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 39 of 93 Name of task 280. Load test monorail track Exposed people Local dose rate 1 µSv/hr Workforce 4 people Time needed 2 hours Calculated dose Responsible EN-HE Involved EN-HE/ HSE Comments: Replaced Rail...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 40 of 93 Name of task 290. Remove supporting cover over Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: The cover was replaced for task 270, so it needs to be removed for the next operations.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 41 of 93 Name of task 300. Remove support frame for vacuum chamber 1 88 kg Exposed people Local dose rate 10 µSv/hr Storage well Workforce 2 people Time needed 30 min Calculated dose Responsible EN-EA...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 42 of 93 Name of task 310. Remove square shielding Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 4 hours Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: These need to be removed using the monorail.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 43 of 93 Name of task 320. Remove support for square shielding 340 kg Exposed people Local dose rate 10 µSv/hr Workforce 2 people Time needed 1 hour Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 44 of 93 Name of task 330. Drain upper section of pipes from the cooling station Exposed people Local dose rate 10 µSv/hr Workforce Time needed Calculated dose Responsible EN-CV Involved EN-CV/ EN-EA/ EN-HE/ HSE-RP Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 45 of 93 Name of task 331. Remove round shielding block 4 Exposed people Local dose rate Round Workforce 2 people shielding Time needed 0.5 days block 4 Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 46 of 93 Name of task 332. Install the solid version of round shielding block 4 Exposed people Local dose rate Workforce 2 people Time needed 0.5 days Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 47 of 93 Name of task 335. Drill and drain the pipes at the top Exposed people Local dose rate Workforce 2 people Time needed 1 day Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 48 of 93 Name of task 336. Remove solid version of shielding block 4 Exposed people Local dose rate Workforce 2 people Time needed 0.5 days Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP Comments: Remove the shielding block that was installed in task...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 49 of 93 Name of task 340. Remove round shielding blocks 3 and Specific hoisting beam Exposed people Local dose rate 10 µSv/hr Workforce 2 people Time needed 1 day 2.3 t Calculated dose Responsible EN-EA...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 50 of 93 Name of task 350. Remove shielding block 1 Exposed people Local dose rate 500 µSv/hr Workforce 2 people Time needed 2 hours Calculated dose Responsible EN-EA Involved EN-EA/ EN-CV/ HSE-RP Comments: This task will be performed from the Technical Gallery.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 52 of 93 Name of task 355. Install the solid version of shielding block 1 Exposed people Local dose rate 70 µSv/hr Workforce 3 people Time needed 1 hour Calculated dose Responsible EN-EA Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 53 of 93 Name of task 360. Remove pipe retaining screws Exposed people Local dose rate 100 µSv/hr (see comment) Workforce 3 people (1 down, 1 or 2 in Tech Gallery) Time needed 5 min Calculated dose...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 54 of 93 Name of task 370. Pull pipes away from wall Exposed people Local dose rate 100 µSv/hr Workforce 3 people (1 down, 1 or 2 in Tech Gallery) Time needed 5 min Calculated dose Responsible...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 55 of 93 Name of task 380. Remove bracket top plates Exposed people Local dose rate 100 µSv/hr Workforce 3 people (1 down, 1 or 2 in Tech Gallery) Time needed 10 min Calculated dose Responsible...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 56 of 93 Name of task 390. Fix pipes out of the way against wall Exposed people Local dose rate 100 µSv/hr Workforce 3 people (1 down, 1 or 2 in Tech Gallery) Time needed 10 min...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 57 of 93 Name of task 400. Pump out water from this level Exposed people Local dose rate 100 µSv/hr Workforce 3 people Time needed 20 min Calculated dose Responsible EN-CV Involved EN-EA/ EN-HE/ HSE-RP/ EN-CV/ EN-STI...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 58 of 93 Name of task 410. Remove ladders and equipment and prepare for the removal of the block Exposed people Local dose rate 10 µSv/hr Workforce 3 people Time needed 15 min Calculated dose Responsible...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 59 of 93 Name of task 420. Remove solid version of round shielding block 1 Exposed people Local dose rate 70 µSv/hr Workforce 2 people Time needed 2 hours Calculated dose Responsible EN-STI Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 60 of 93 Name of task 430. Remove centring plate Exposed people Local dose rate 100 µSv/hr Workforce 2 people Time needed Calculated dose Responsible EN-STI Involved EN-STI/ EN-HE/ HSE-RP Comments: This was not secured when it was installed.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 61 of 93 Name of task 440. Raise target to technical gallery whilst pipes are cut Exposed people Local dose rate 2000 µSv/hr Workforce Time needed 1.5 days Calculated dose Responsible EN-STI Involved EN-STI/ EN-SMM/ EN-HE/...
Page 62
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 62 of 93...
Once the pipes are cut, and while the target is hanging from the monorail, RP will perform measurements and a smear test. The work will be performed remotely. The CERNbot will be equipped with a robotic arm, which mounts in the gripper the RP sensor. Model: ATOMTEX BDKG-24.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 64 of 93 Name of task 460. Remove the target from the Tech Gallery and lower it through the trapdoor into the draining tray Exposed people Local dose rate 2000 µSv/hr Workforce Time needed Calculated dose...
Page 65
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 65 of 93...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 66 of 93 Name of task 470. Drill hole in target to drain moderating circuit Exposed people Local dose rate 2000 µSv/hr Workforce 4 people Time needed 2 hours Calculated dose Responsible EN-STI Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 67 of 93 Name of task 480. Drill holes in target to drain cooling circuit Exposed people Local dose rate 2000 µSv/hr Workforce 4 people Time needed 2 hours Calculated dose Responsible EN-STI Involved...
Page 68
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 68 of 93...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 69 of 93 Name of task 490. Lift the target, place it in the Tech Gallery Exposed people Local dose rate 2000 µSv/hr Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP Comments: This is to be done by the monorail hoist in the...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 70 of 93 Name of task 500. Lower the target inside the shielding box Exposed people Local dose rate 2000 µSv/hr Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP Comments: All the equipment from the draining (water containers, draining tray, spacer blocks) will be...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 71 of 93 Name of task 510. Pull the target out from below the trap door Exposed people Local dose rate 2000 µSv/hr Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP Comments: This will be done by electric tractor and tow bar...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 72 of 93 Name of task 520. Take the shielding box out of the trolley, and into the PSI container Exposed people Local dose rate 2000 µSv/hr Workforce Time needed Calculated dose Responsible EN-STI Involved...
Page 73
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 73 of 93...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 74 of 93 Name of task 530. Remove the PSI container out of ISR8 Exposed people Local dose rate 100 µSv/hr Workforce Time needed Calculated dose Responsible EN-HE Involved EN-EA/ EN-HE/ HSE-RP Comments: The PSI container can then be transported in the RP- RW premises (ISR6) and stored safely with concrete...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 75 of 93 Name of task 540. Place sections of cut pipe inside containers. Exposed people Local dose rate Workforce Time needed Calculated dose Responsible EN-SMM Involved EN-EA/ EN-HE/ HSE-RP Comments: The sections of pipe that were previously cut and left in the Technical Gallery can now be wrapped and placed in containers (one container for moderating...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 76 of 93 Name of task 550. Place the solid shielding block 1 back in the pit Exposed people Local dose rate 70 µSv/hr Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 77 of 93 Name of task 560. Cooling pipes removal. Disconnect the 4 pipes Exposed people Local dose rate Workforce Time needed 20 min Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN-CV Comments: It’s difficult to predict the dose rate in this...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 78 of 93 º Name of task 570. Disconnect the lower end of the pipes Exposed people Local dose rate Workforce Time needed 10 min Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN-CV Comments: Remove the bindings that were installed in Task 390 to keep the flexible sections out of the way.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 79 of 93 Name of task 580. Place slings on the moderating and cooling water pipes to support them. Exposed people Local dose rate Workforce Time needed 10 min Calculated dose Responsible EN-STI Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 80 of 93 Name of task 590. Remove the supports attaching the pipes to the wall Exposed people Local dose rate Workforce Time needed 20 min Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN-CV Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 81 of 93 Name of task 600. Remove the pipes using the monorail Exposed people Local dose rate Workforce Time needed 10 min Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN- Comments: The pipes could go out in one piece it the monorail drags them along the Tech Gallery (a...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 82 of 93 Name of task 610. Cut the pipes and place them into containers Exposed people Local dose rate Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN-CV/ EN-SMM Comments: It is not clear if the pipes will need to be cut.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 83 of 93 Name of task 620. Pipe assembly removal, cooling station side Exposed people Local dose rate Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN- Comments: The pipes connecting the cooling station to the pit form one assembly.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 84 of 93 Name of task 630. Pipe assembly removal, pit side Exposed people Local dose rate Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN- Comments: Similar to the previous task. Remove the silicone, and remove the fasteners that fix the circular plate to the wall.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 85 of 93 Name of task 640. Pipe assembly removal, extraction and cutting Exposed people Local dose rate Workforce Time needed Calculated dose Responsible EN-STI Involved EN-EA/ EN-HE/ HSE-RP/ EN-CV Comments: The extraction of the complete assembly has to be done from the cooling station side.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 87 of 93 NOTE: The following tasks will be carried out separately, in 2020, during the installation of Target #3. Name of task 660. Remove dump core insert Exposed people Local dose rate 0.1 µSv/hr Workforce 2 people...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 88 of 93 Name of task 670. Remove Cap around outer beam dump Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 0.5 days Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE Comments:...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 89 of 93 Name of task 680. Remove outer dump blocks Exposed people Local dose rate 0.1 µSv/hr Workforce 3 people Time needed 4 hours Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE Comments: Installed with mobile crane.
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 90 of 93 Name of task 690. Remove inner beam dump blocks Exposed people Local dose rate 0.5 µSv/hr Workforce 4 (Depending on weight of blocks) Time needed 30 minutes Calculated dose Responsible EN-EA Involved...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 91 of 93 Name of task 700. Remove dump concrete ring (+ vacuum chamber) Exposed people Local dose rate 0.5 µSv/hr Workforce Time needed Calculated dose Responsible EN-EA Involved EN-EA/ EN-HE/ HSE-RP Comments: Installed from the top with a mobile crane and ‘standard M16 lifting equipment.’...
REFERENCE EDMS NO. REV. VALIDITY TOF-TAR-PRD-0001 1867100 RELEASED Page 92 of 93 Name of task 710. Remove support plate Exposed people Local dose rate 0.1 µSv/hr Workforce 2 (An extra pair of hands may be needed to support the plate) Time needed Calculated dose Responsible...