Advertisement

Quick Links

myPV CommsSafe™ User
Manual
Resources
Design Considerations
Receiving
Network Integration
Pre-Energization Checks
Initial Energization
Commercial Operation
Spare Parts
Torque Schedules
Troubleshooting
myPV CommsSafe™ User Manual
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CommsSafe AC-1 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for MYPV CommsSafe AC-1

  • Page 1 CommsSafe™ User Manual Resources Design Considerations Receiving Network Integration Pre-Energization Checks Initial Energization Commercial Operation Spare Parts Torque Schedules Troubleshooting myPV CommsSafe™ User Manual...
  • Page 2 Technical Documents page by registering on our Support Resources page. Product Line Specifications The myPV CommsSafe product line is available in three (3) options of power supply that are determined by the customer auxiliary power availability. The CommsSafe covers all networking aggregation and options for monitoring.
  • Page 3 Example: myPV CommsSafe 2021 - AC-1ø Shown Resources...
  • Page 4 Standard Technical Specifications: While myPV CommsSafe products all are able to be customized to meet your needs - the frame sizing and design layouts are arranged in the same manner. The following photos provide a visual reference for some common locations of common features.
  • Page 5 Back Panel for CommsSafe in Production - Shown with Customer Supplied Equipment Added Resources...
  • Page 6: Design Considerations

    Installation Location The installation location for the myPV CommsSafe is easy to locate on the solar site. A concrete pad with a standard unistrut is built on site during initial construction - and is designed to be the installation location for the myPV CommsSafe.
  • Page 7 The three phase power or 120V power should be terminated in the bottom left of the cabinet. Refer to the Quick Start Guide for more information. All three power supply levels of the myPV CommsSafe are rated for a control panel SCCR level of 10KA.
  • Page 8 Whip installation is easy - our whips come pre-terminated; however in the event that they are not or you need to do some troubleshooting, follow these steps. 1. Separate the different wire colors in the whip - to make sure you can see them all in front of you.
  • Page 9 Arrival The Customer is responsible for receiving and unloading of all equipment deliveries. The myPV CommsSafe will arrive in a sealed box - and is ready for installation as soon as the package is opened. Whenever possible, your Solar-Ops Account Manager will share tracking information and put the driver directly in contact with the receiving party for receiving coordination.
  • Page 10 This guide walks you through every step on how to safely, and securely attach your myPV CommsSafe to the Unistrut utilizing the predrilled feet on the back of the cabinet, install your sensors, and successfully and safely terminate the power. Do not modify the cabinet to mount it or it will no longer be weather proofed.
  • Page 11: Network Integration

    CommsSafe™ is intended to be a first class “Connected Plant” device. Overview The myPV CommsSafe may be added to the local area network (LAN) via an integrated network switch. All internal networkable devices are connected to that central switch and may be accessed via MODBUS TCP/IP, Web-Hosted Interface, or Vendor Provided Software.
  • Page 12 Media Connection Ethernet and/or fiber media will need to be terminated and tested by the installer, and connected to the network switch inside the Control Cabinet. Standard 8-Port Switch Optional MM Fiber Switch *Other Options Available Network Integration...
  • Page 13: Device Communications

    Device Communications The myPV CommsSafe supports multiple communication options for all networkable devices to support: third-party monitoring, SCADA, and even IT reporting requirements. Communications Options Default IP Purpose Accessibility Device Media Address RV50X Cellular Modem 198.162.1.100 RJ45 Admin Web HMI (9191) Edge myPV IQ™...
  • Page 14: Pre-Energization Checks

    Pre-Energization Checks Before you energize the myPV CommsSafe for the first time, let’s verify everything is ready for initial commissioning. Skills and Tools Required Commissioning Staff should be prepared to: Physically Open the Cabinet Continuity Test Fuses Electrically Test Equipment Grounding...
  • Page 15 2. OPEN (by pulling the top and swinging down) the DC Bus Fuse Holder, leave OPEN Use a multimeter to verify fuse *continuity for 3. (Shipped, not installed) Verify both battery fuses for continuity Install both battery fuses, leave installed Three (3) spare AC fuses are included in the orange envelope mounted on the back of the Control Panel swing door* One (1) spare DC battery fuse is included in the orange envelope mounted on the back of the Control Panel swing door...
  • Page 16 Reference the image number callouts for additional verification locations: 1. Perform a gentle control wiring pull test of the AC control power terminations 2. Perform a gentle control wiring pull test of the sensor connectors from the Heyco’s Control Panel Wiring Pull Test Locations Once operational - please contact our development team to help make sure that all software, monitoring, and data collection sections are prepared and ready to begin active operation.
  • Page 17: Initial Energization

    Pre-Energization Checks. If you have not yet performed the Pre-Energization Checks, or have taken any actions that altered the as-left conditions of the myPV CommsSafe™ set forth at the completion of the Pre-Energization Checks, we strongly recommend performing the Pre- Energization Checks before proceeding.
  • Page 18 Everything in box is 120VAC or 24VDC Utilize this wire key: Controls Energization Energizing the Control Panel will also energize the Meter and Protective Relay, enabling addition commissioning verifications. Addition Commissioning Verifications: 1. Proper Battery UPS Energization 2. Networking & SCADA Equipment Energization 3.
  • Page 19 24V DC (±0.1V, 23.9 - 24.1V) voltage on the top (input) terminals of the UPS Initial Energization...
  • Page 20 24V DC (-0.1V/+6.0V , 23.9 - 30.0V) voltage on the top (battery) terminals of the UPS Initial Energization...
  • Page 21: Recommended Maintenance Schedule

    Commercial Operation The myPV CommsSafe is designed to require as little maintenance possible, but like any equipment a little care ensures proper operation and a long life of reliable service through the life of your Facility. Recommended Maintenance Schedule The myPV CommsSafe is designed to be maintenance free, and requires no regular consumables or maintenance service under normal operational conditions.
  • Page 22: Spare Parts

    Spare Parts The myPV CommsSafe is designed with high quality, industrial grade, components that are intended to provide reliable operation throughout the commercial operating lifespan of your facility. Having a selection of spare parts on hand, however, can prevent unnecessary prolonged downtimes.
  • Page 23 Torque Schedules The myPV CommsSafe was designed to be mechanically assembled using the following torque schedules. For all bolted connections, unless otherwise specified, refers to the chart below. For electrical components, see component manufacturer’s data for all screw terminal tightening torques.
  • Page 24: Troubleshooting

    Eliminate the most common myPV CommsSafe operational issues quickly and safely. No AC Power If there is no AC power showing for your myPV CommsSafe there are a few main things this could be attributed to. First - check for any blown fuses - these fuses will often have an indicator LED light that should illuminate given any issues;...
  • Page 25 A fully seated fuse that is not blown in the AC block. Troubleshooting...
  • Page 26 TEMPERATURE SENSOR WIRE: If all fuses are seated properly and are not blown, check to see if the temperature sensor wire is firmly seated. Occasionally in transport this wire can become loose. In the event that the temperature sensor wire is loose;...
  • Page 27 A Fuse Terminal block that is fully connected to the rest of the AC Block JUMPERS: If the fuses are not the issue, verify that all jumpers are in their terminal blocks and seated securely. Troubleshooting...
  • Page 28 POWER SUPPLY: After checking the jumpers and the fuses, there is a small chance that the power supply itself might be dead. Contact the myPV Support Team if you believe this to be the concern or can not identify the issue.
  • Page 29 When working with the myPV CommsSafe, communication with your equipment is essential. However, in the event that the ethernet comms seem to be out, there are a few things to try. CONNECTORS: First and foremost, verify the color order of the conductors and the connectors;...
  • Page 30 Please note for troubleshooting device issues, there is a standard device ID numbering system regardless of the number of devices with which your myPV CommsSafe is communicating. POA - Device ID 1 GHI - Device ID 2 BOM - Device ID 3...

This manual is also suitable for:

Commssafe ac-3Commssafe ac-1.5k

Table of Contents