5. Advice for Installation

The controller has to be installed possibly near the battery and must not be
exposed to direct weather conditions. The controller is to be operated in well-
ventilated rooms. The connection terminals have to point downwards when it is
installed. In order to activate the protective functions the controller has to be
connected with solar generator, battery and user.
All system components i.e. solar generator, battery users and controller have to
be coordinated concerning voltage. This is to be checked before installation.
Pay attention to the correct nominal voltage. Ask your dealer when you are in
doubt.
6. Connection
WARNING
Danger of explosion from sparking! Danger of electric shock!
Solar modules generate electricity under incident light. The full voltage is
present even when the incident light levels are low.
Protect the solar modules from incident light during installation, e. g.
cover them.
Never touch un-insulated cable ends.
Use only insulated tools.
Ensure that all loads to be connected are switched off. If necessary,
remove the fuse.
Connections must always be made in the sequence described below.
Solar
SOLAR CHARGE CONTROLLER
2
yellow
red
green
Load
empty
full
SOLAR SCG 1010
12/24V
10A
1
3
Connection sequence
1. battery
2. solar module
3. loads