Page 1
OPERATING INSTRUCTIONS Transport and installation Transport and installation instructions TNX65/42 142853 - 22.10.2021 10.21/Ru (Transport- und Aufstellanleitung) - 20057384...
Page 2
Note on applicability Illustrations in this publication may deviate from the product supplied. Errors and omissions due to technical progress expected. A word on copyright This document is protected by copyright and was originally compiled in German. The duplication and distribution of this document or parts thereof is prohibited without prior consent of the copyright owner, and any violators will be prosecuted.
Installation diagram ..........................General data General data ......................................................Dimensions (without additional attachments) ................... TNX65/42 / TNX65/42 with milling unit ..................Machine weight and machine dimensions ..................TNX65/42 ............................TNX65/42 with milling unit ......................Bearing points* ..........................Information on transporting the machine by truck ................
Page 4
Installation of the tool chain and chain magazine (only with optional 120 positions) ......Install upper part of chain magazine ....................Connect the chain of the chain magazine (only with optional 120 positions) ........Install cover on milling unit with tool changer ................... Fuels Fuels ............................................................ Overview of fuels ..........................TNX65/42 22.10.2021...
Page 5
Check / correct with tool carrier 2 ....................Secure machine to the floor ......................Transport and installation of the chip conveyor ................. Setting the level switch of the chip conveyor ................... Lubricoolant unit ..........................Bar feeding mechanisms ........................Switching on the machine ......................... TNX65/42 22.10.2021...
Documentation safety instructions The documentation for users and particularly the safety instructions must be observed. The safety instructions are set out in a separate document forming part of the TRAUB documentation for users. TNX65/42 10.2016...
Installation and layout diagrams The corresponding installation and layout diagram must be obtained before the machine is installed. Layout diagram Drawing No. 478503 6900 Scale 1:50 M. 1:50 1900 Scale 1:100 M. 1:100 = Electrical connection = Operator side Illustration exemplary TNX65/42 10.2016...
When using a fork lift truck, it must be lifted from the operator side. The machine with bar loading magazine must in all cases be anchored in the ground. Dimensions (without additional attachments) TNX65/42 / TNX65/42 with milling unit Length of foundation 3690 Width of foundation...
General data TNX65/42 with milling unit Machine weight without control cabinet 8800 with control cabinet 10000 Machine dimensions Length (without chip conveyor) 4744 Width without control console 2365 Width without working area door handle 2330 Height 2700 / 3461 Operating altitude...
• All doors on the machine must be able to open completely. • Space for pallets containing blanks and workpieces, workpiece containers, chip trolleys, tool trolleys, etc. The space required can be determined with the aid of the installation drawing. TNX65/42 22.10.2021...
A sturdy container is needed to collect the extracted fluids. Tightly closing and duly labelled metal containers of corresponding capacity can be used for this purpose. TNX65/42 22.10.2021...
Electrical connection External data transmission Data lines must not be located directly alongside power lines. Suitable metal conduits must be installed for the data line in order to transmit data from/to external computers and storage systems. TNX65/42 22.10.2021...
For this reason, the machine's installation site must be designed to prevent any harmful effects on bodies of water or the groundwater due to these substances. Possible precautions • Place the machine in a leak-proof steel pan (bottom sump). • Seal the floor of the factory hall. TNX65/42 22.10.2021...
Before delivery, all machines are coated to protect them from corrosion. This corrosion protection must be renewed accordingly whenever the machine is subsequently transported again. Details on corrosion protection can be found in the documentation Notes on Operating Materials. TNX65/42 22.10.2021...
The transport retainers are located on the: • control console • tool carrier and opposed spindle • sliding door • workpiece handling with remnant removal device Workpiece handling with remnant removal device Transport retainers for working area door Tool carrier and opposed spindle TNX65/42 22.10.2021...
(The locking plate must be retained by the customer in case the machine has to be transported again). • Fit the M12 cheese head screw at the pivot point of the control cabinet. • Fit the fixing screw inside the control cabinet. TNX65/42 22.10.2021...
Page 22
Preparing to transport a machine without milling unit Ensure that the four wheels on the control cabinet have been screwed in completely. TNX65/42 22.10.2021...
Preparing to transport a machine with milling unit Transport retainers Transport retainers must be fitted to secure the machine for transport. Position of the transport retainers Transport retainer, turret / milling unit / main and opposed spindle Transport retainer, workpiece handling TNX65/42 22.10.2021...
Page 24
Preparing to transport a machine with milling unit Transport retainer, tool changer TNX65/42 22.10.2021...
Min. fork length 1000 Max. fork width Forks adjustable to a minimum distance of Disassembly • Remove the connecting bar between the chain magazine and the machine. • Remove the cover over the chain magazine. Cover Connecting bar TNX65/42 22.10.2021...
Remove the cover on the milling unit with tool changer Disconnect the cables from the cover to the machine. Unscrew the cover of the milling unit with tool changer at the five retaining points and remove it. Cover Cover TNX65/42 22.10.2021...
• Remove the circlip from each connecting pin and take out the front bearing. Push the connecting pins through and remove them with the rear bearing. 4. Take out Connecting pin bearing 2. Take out bearing 1. Remove circlip 3. Push connecting pin through TNX65/42 22.10.2021...
A suitable fork lift truck can also be used instead of a crane. In this case, two brackets must be screwed onto the M12 threads provided for this purpose (the brackets Art. No. 095662 are available on loan from TRAUB). • Take out the six screws on each side of the chain magazine.
• The central lubrication system is filled, the hydraulic and cooling units are empty. Ensure that the four wheels on the control cabinet have been screwed in completely. • Machine components and accessories mounted on pallets and secured TNX65/42 10.2016...
The machine must not be lifted via the control cabinet! View of the machine in transport condition Retaining plate Remove handle Plank Carriage bolts M16x260 with nut Plate for attaching the hydraulic jack Wheels on control cabinet raised TNX65/42 10.2016...
Transporting the machine Set of hoisting gear and fittings The complete set of hoisting gear and fittings (Article No. 083435) is available from TRAUB on loan and must be returned completely and without delay after use. Suspension points, front view Cross-arm assy., load capacity 15 t...
Centre of gravity Version Tool carrier Overall weight top left bottom right 9.760 t -222 top right bottom left 1 top left 8.326 t 467.5 -233 2 bottom right top left bottom right 9.041 t -255 bottom left TNX65/42 10.2016...
When setting down the machine, ensure that the fork arms are not inclined, otherwise the planks may break. To prevent damage to the machine, the rear wheel must be removed from the control cabinet before transporting it. TNX65/42 10.2016...
The load must be secured so that it cannot slip. Measures to prevent the load slipping • Non-slip rubber mat between loading surface and machine. • The machine base must be diagonally lashed to the loading surface with suitable lashing straps / chains. TNX65/42 10.2016...
• Lift the machine by crane and secure it with suitable supports. • Unscrew the wooden planks. Ensure that the four wheels on the control cabinet have been screwed in completely. • Lift the machine (remove the supports) and slowly lower it onto the feet. TNX65/42 22.10.2021...
Each hydraulic jack must be able to support a full load of 10 t. Three rollers are required for transport, including one steerable roller. The rollers must be dimensioned for loads of up to 12 t. The rollers must always be positioned parallel to the material being hoisted. Transport diagram TNX65/42 22.10.2021...
• The distance from the floor must equal 70 mm at all four installation points. • Adjust the four outer feet and align the machine with the aid of the spirit level. • Secure the adjusting screws of the feet with the locknuts. TNX65/42 22.10.2021...
(The locking plate must be retained by the customer in case the machine has to be transported again). • Unscrew the M12 cheese head screw at the turning point of the control cabinet. • Take out the fixing screw in the control cabinet. TNX65/42 22.10.2021...
Ensure that the wheels are at right angles to the pivot point and secure the wheels with locknuts. Wheels Machine • The control cabinet can now be swivelled to the rear. Indicator lamp Connect the indicator lamp on the machine if removed for transport. TNX65/42 22.10.2021...
• workpiece handling with remnant removal device • tool carrier and opposed spindle Transport retainers • Working area door • Workpiece handling with remnant removal device Workpiece handling with remnant removal device Transport retainers for working area door TNX65/42 22.10.2021...
Transport retainer for turret (tool carrier / main spindle and opposed spindle / milling unit) Transport retainer for turret / main spindle and opposed spindle Transport retainer for turret / milling unit / main spindle and opposed spindle TNX65/42 22.10.2021...
Page 42
Installing the machine Transport retainer for workpiece handling TNX65/42 22.10.2021...
Page 43
Installing the machine Transport retainer for tool changer if necessary TNX65/42 22.10.2021...
Page 44
Installing the machine TNX65/42 22.10.2021...
A suitable fork lift truck can also be used instead of a crane. In this case, two brackets must be screwed onto the M12 threads provided for this purpose (the brackets Art. No. 095662 are available on loan from TRAUB). Requirements to be met by a fork lift truck Min.
Page 46
Installation of the milling unit components • Secure the chain magazine on both sides with the six screws provided. TNX65/42 10.2016...
The tool chain must be secured at the separating points by suitable means so it cannot fall down. Two openings are provided in the tool magazine for fitting the connecting pins of the chain links. Openings for fitting the connecting pins of the chain links TNX65/42 10.2016...
Page 48
• Push through the connecting pin with bearing and fit the bearing on the opposite side. • Attach the circlip to the connecting pin. 1. Push through connecting pin with bearing Connecting pin 2. Insert bearing 3. Attach circlip TNX65/42 10.2016...
Installation of the milling unit components Install cover on milling unit with tool changer Attach the cover of the milling unit with tool changer and secure it at the five fixing points. Reconnect the cables to the machine cover. Cover Cover TNX65/42 10.2016...
Page 50
Installation of the milling unit components • Position the cover on the chain magazine with suitable aids and secure it. • Refit the connecting bar. Cover Connecting bar TNX65/42 10.2016...
Designation Initial start-up [litres] Factory-filled by Central lubrication TRAUB Hydraulic system Lubricoolant unit Note the corresponding manufacturer's To be provided by the documentation customer See chapter Pneumatic connection Compressed air Bar loading magazine Note the corresponding manufacturer's documentation TNX65/42 10.2016...
The values can be read off on pressure gauges to check normal functioning. Air consumption The air consumption depends on the machine's equipment configuration and cycle time. A value of 200 - 300 Nl/min (without window clearing blower) is assumed on average for a standard machine. TNX65/42 10.2016...
• The control voltages are connected to the PE on one side in accordance with EN 60204 Part 1 (VDE 0113). Please note the instructions in the circuit diagram. TNX65/42 05.2017...
Precision adjustment of the machine is carried out with the aid of a fixture inserted in the turret on tool carrier 2. Spirit levels with an accuracy of 0.02 mm/m are placed on this fixture in Z and X directions in order to check the machine’s position and torsion. TNX65/42 10.2016...
• Secure the adjusting screws of the feet with the locknuts. Switch off the control system, disconnect the machine from the power supply and secure it so that it cannot be reactivated. TNX65/42 10.2016...
(Article No. 318181) in the hole. The machine is anchored to the foundations by tightening down the hex bolt with the specified torque (approx. 80 Nm). Bottom box 469193 Bracket 318181 Dowel pin 687403 Ring TNX65/42 10.2016...
Note the User Manual (parameter list) provided by the manufacturer. Bar feeding mechanisms Note the corresponding manufacturer's documentation The bar feeding mechanisms and other accessories must be mounted, aligned and secured to the floor as directed by the respective manufacturers. TNX65/42 10.2016...
• Switch drives ON. • Open and close working area door Operability of the door switches must be checked by opening and closing the working area door. Operation of the machine cannot be commenced until the safety facilities have responded. TNX65/42 10.2016...
Page 62
Alignment, component installation and commissioning TNX65/42 10.2016...
Page 64
INDEX-Werke GmbH & Co. KG Hahn & Tessky Plochinger Straße 92 D-73730 Esslingen Fon +49 711 3191-0 Fax +49 711 3191-587 info@index-werke.de www.index-werke.de...
Need help?
Do you have a question about the TNX65 and is the answer not in the manual?
Questions and answers