3.2. Electrical Wiring
3.2.1. 230V Single-Phase
The L,N and PE should be wired according to local requirements.
The phase used must measure 230V (±10%).
WARNING: Each ground must be connected to neutral
at only one point, or the EV charger cannot operate.
WARNING: Before installing the Amstel Dock, identify
the type of utility service connection available on site. If
you are unsure about the type of connection available
at the service panel, consult an electrician for
assistance.

3.3. Installation Considerations

Three configurations are available to install the Amstel Dock:
The location of the conduit determines which installation method to
follow. If the conduit runs along the floor or low to the wall, use the
bottom entry configuration. If the conduit comes from inside the
wall, use the rear entry configuration. If the available conduit comes
from the ceiling, use the top entry installation.
Note: Throughout the manual, "conduit" is used as the standard
term for the protective tubing that houses the service wiring. In
regions where conduit is not used (Europe for example), a cable
comprised of service wiring enclosed in a protective jacket may be
substituted for conduit if allowed by local regulations.
Here are some additional guidelines:
Conduit openings are sized for 32mm conduit.
Conduit needs to be metal and flame retardant.
Use an appropriate circuit breaker.
To keep the housing waterproof, use cable glands.