Please read these instructions throughout before installing as incorrect fitting will invalidate the guarantee.
If you are unsure about these instructions please contact Barwick Bathroom Distribution LLP 01274 687555.
DUE TO THE WEIGHT & SIZE OF THE GLASS PANEL(s) A MINIMUM OF TWO PERSONS ARE REQUIRED
Tools Required
Pozi-head Screwdriver
7mm Masonry Drill Bit
Spirit Level
Scissors
Hacksaw
STRAIGHT PIVOT DOOR, CORNER
www.sommershowers.co.uk
HEALTH & SAFETY WARNING
TO MOVE AND INSTALL THIS ENCLOSURE
Clear Silicone Sealant
Drill (Battery or Mains)
Tape Measure
Pencil
800, 900, 1000, 1200, 1400
Installation Instructions
Cleaning - General
For the wall post and fixings use only warm soapy water and damp cloth/ sponge
on a regular basis. After cleaning please rinse with clean water to remove any
residue.
Do not use abrasive scouring powders, chemicals or aerosol cleaners - these may
result in damage to the surfaces, in particular, the plated component parts.
Glass Treatment
The glass panels are pre-treated with a protective coating on the inside surfaces
only. Whilst this makes cleaning the glass easier and helps prevent the build up of
harmful lime-scale and soap deposits, the glass still needs to be maintained on a
regular basis. We recommend the use of a detergent and aroma free glass cleaner
(A 50/50 mix of white vinegar and water works well)
DO NOT use strong detergents, abrasive cleaners or abrasive scrubbing
equipment for cleaning, these can damage the coating.
DO use a squeegee to remove remaining droplets of water from glass after
showering, any build up of residue can be removed easily using an appropriate
cleaner and agitation from soft cleaning equipment
Important
Check appearance of all product - any defects must be reported to your retailer
before assembly/installation. Claims for imperfections will only be accepted prior
to assembly/installation.
Any claims made under the terms of the Lifetime Guarantee
must be reported to your retailer within 21 days of the fault occurring
Check the enclosure adjustment sizes are suitable for your installation.
Use care when drilling into the walls to avoid hidden pipes or electric cables.
Shower Tray
Ensure the top of shower tray is
LEVEL in ALL directions.
Once the tray is installed but
before the wall tiles are fitted, any
gap between the tray and the walls
must be filled with silicone sealant
flush with the top of the tray.
Once the walls have been tiled but
before the enclosure is installed,
the tiles must be silicone sealed to
the tray all of the way around in
one continuous bead.
Failure to follow these
instructions will result in
leakage problems.
THESE INSTRUCTIONS ARE TO BE LEFT
WITH THE CONSUMER
1
silicone sealant
Stage 1
Stage 2
Issue 02 DEC.20

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 800 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for SOMMER 800

  • Page 1 STRAIGHT PIVOT DOOR, CORNER 800, 900, 1000, 1200, 1400 Installation Instructions www.sommershowers.co.uk Please read these instructions throughout before installing as incorrect fitting will invalidate the guarantee. If you are unsure about these instructions please contact Barwick Bathroom Distribution LLP 01274 687555.
  • Page 2 Product Sizes and Adjustments PRODUCT PACK CODES DIMENSIONS (mm) PIVOT CORNER IN-LINE DOOR PACK PANEL PACK PEV1(C/BK) PEVX(C/BK) 775 to 795 PEV2(C/BK) PEVX(C/BK) 875 to 895 1000 PEV3(C/BK) PEVX(C/BK) 975 to 995 1200 PEV4(C/BK) PEVX(C/BK) 1175 to 1195 1400 PEV5(C/BK) PEVX(C/BK) 1375 to 1395 PRODUCT...
  • Page 3: Parts List

    Parts List Door Pack for Recess & Corner 1 x PD199 Threshold Strip 1 x M500-01/02 1 x M501-01/02 3 x M506-01 3 x M507-01 1 x M502-01 1 x M503-01 PD199 End Cap, PD199 End Cap, Wall Post Screw Wall Post Screw End Cap End Cap...
  • Page 4 Step 2 - Position and Mark Wallposts 1. Position wallpost for door (with side slots to inside) 9mm in from front edge of tray, as shown below. Using spirit level to ensure wallpost is vertical, mark through the 5 slots onto the wall surface as shown and remove wallpost. Important to mark the holes as indicated in red below, to the ends of the slots. 2.
  • Page 5 Step 5 - Fit Bottom Trim To Side Panel 1. Take note of label ‘This surface to outside’ this will determine which is the bottom edge of your installation. 2. Acquire the WTR-0001 Trim from the Side Panel Pack. Peel off a small length of the bottom trim adhesive tape and apply to bottom of glass panel 15mm from the end that will be going into the wallpost, as shown.
  • Page 6 Step 9 - Position Door Assembly Step 10 - Fix Door Assembly 1. Take the three ‘Wallpost Screw Mouldings’ from the Door 1. Carefully fit Door Glass Assembly into wallpost. Slot the glass into the ‘BLOCK’ already Installation Pack and place them into the slots on the Door Wallpost positioned, as shown.
  • Page 7 Step 15 - Trim Stabiliser Rail (if required) 1. Measure distance from INSIDE face of side panel to side wall, as shown. Deduct 5mm from this measurement and transfer this to the stabiliser rail. Example: ‘Y’ = 760mm minus 5mm = 755 to mark on rail 2.
  • Page 8: Outside View

    Step 17 - Prepare Door Seal PLEXRF-052 Step 18 - Add Door Seal PLEXRF-052 1. Acquire PLEXRF-052 from the Door Pack. Cut the corners of the rigid flipper 1. Add the prepared Door Seal PLEXRF-052 to the bottom edge of the at 45 degree angle, as shown below.
  • Page 9 Step 24 - Silicone and Apply Water Threshold Strip Step 25 - Silicone 1. On the outside, silicone around all three junctions with the wall and tray, Before carrying out these last steps make sure you are happy with the and also on the wallposts where the sill meets the uprights.