15.2 Preventive Maintenance Schedule
Consult the following preventive maintenance schedule for daily, weekly, and monthly maintenance tasks:
ITEM
MOTORS
GREASE MOTORS OPERATING ABOVE 70
ELECTRICAL
CABLES
SCREEN
GASKETS
DECK
ADJUSTMENT
CHECK FOR FULL UP AND DOWN TRAVEL
SYSTEM
SUPPORT
SPRINGS
SCREEN HOLD
DOWN BAR
GASKET
GROMMETS
NUTS AND
BOLTS
MOTOR BOLTS
DECK
ADJUSTMENT
SYSTEM
TIME INTERVALS ABOVE ASSUME CONTINUOUS SHAKER OPERATION.
NOTE
30
Field Installation and Operation Manual 9092F02001AENG (D)
MONGOOSE PRO Shale Shaker
Table 3. Recommended Preventive Maintenance Schedule
TASK
GREASE MOTORS OPERATING AT
NORMAL TEMPERATURE
APPLY 1.41 OUNCES (40 G)
C (158 F)
APPLY 0.7 OUNCES (20 G)
CHECK FOR WEAR AND DAMAGE
CHECK FOR CRACKS
CHECK FOR UNEVEN COMPRESSION
CHECK SCREWS FOR TIGHTNESS
CHECK FOR HOLDING
CHECK FOR TIGHTNESS
VERIFY PROPER TORQUE
GREASE JACK FITTING
INTERVAL
2000 HOURS RUN TIME
1500 HOURS OF RUN TIME
WEEKLY
MONTHLY
MONTHLY
MONTHLY
MONTHLY
MONTHLY
MONTHLY
MONTHLY
MONTHLY