10 Dismantling and fitting with removed air inlet and gas outlet /
10.12 Installing the cartridge group
Fig. 69: Installing the cartridge group
Product
A150
A155
Table 48: Tightening torque (51007)
8. Coat the threads of the studs (51006) with high-temperature grease.
9. Align casing position of cartridge group with marking and lower into the turbine casing.
10. Remove lifting gear cross-piece of service support.
11. Install the fastening strips (51002) with Verbus Ripp® washers (51003) and hexagon
nuts (51007). Observe the tightening torque.