3. Installation

Mechanical
Modules have 12 clearance holes for mounting screw locations. The modules can be mounted in
any orientation.
General mechanical and mounting information is shown in Figure 1. Please see the datasheet for
additional dimensional information.
Terminal screws: 4 x M5
Maximum torque: 4 Nm
Monitoring terminal screws: 2 x M4
Maximum torque: 2 Nm
For best results the modules should not be mounted in locations where they are directly exposed
to the environment. The modules are compliant to IP-20 standard, for BMOD0010, respectively. In
particular, areas of direct splash should always be avoided. In systems that operate at voltages in
excess of 60 V, appropriate protection and sealing should be used on module terminals to avoid
shock hazards and corrosion. Note that the terminals are fully exposed to the environment.
Dimensional spacings of the mounting holes for the modules are shown in Figures 2. It is
recommended to leave at least 1 cm of spacing between modules along the vertical axis.
User Manual – BMOD0010 E160 B02 – Doc. No. 3003406.1
© 2022 Maxwell Technologies, Inc.
Figure 1: BMOD0010 Mechanical Configuration
Mounting points (12x)
for M5 x 30mm screws
Recommended torque: 4 – 6.2 Nm