Table 14 Wet Cleaning Of Turbines - ABB HT562580 Operation Manual

Table of Contents

Advertisement

Operation Manual / 4 Product description / A130-H.. - A140-H..
6
Periodic maintenance work
Figure 23: Carrying out wet cleaning of turbines
Fulfil prerequisites.
Ensure that the water supply (01) is guaranteed.
Open the stop valve (02) and set the water volume flow V
cleaning parameters).
Close the stop valve (02) after 10 minutes.
Wait for 10 minutes; do not change the load during this stabilisation phase.
If the cleaning result is unsatisfactory or there is water leakage, contact an ABB
Turbocharging Service Station.
Product
Temperature before
turbine before
cleaning [°C]
A130
350 ... 430
A135
350 ... 430
A140
350 ... 430
Table 14: Wet cleaning of turbines, parameters
Corresponds to a water pressure p
1)
© Copyright 2015 ABB. All rights reserved.
Maximum
temperature before
turbine during
cleaning [°C]
530
530
530
of 1.5 bar (overpressure compared to atmosphere)
WT
HZTL4030_EN
with a flowmeter (03) (see
W
Water volume flow
V
[dm
/min]
3
1)
W
4.0
5.5
8.5
Revision C
Page 53 / 115
Injection time
[min]
10
10
10
September 2015