Periodic maintenance work
6.2.5
Carrying out wet cleaning of the compressor
Figure 22: Carrying out wet cleaning of compressor
Engine load
Filling amount of water pressure
50 ... 85 %
Table 12: Parameters for wet cleaning of compressor
Remove sealing plug (27005).
Fill container with 0.4 dm
Screw in sealing plug (27005) again.
Push the valve activator (03) against the spring and hold for 10 ... 15 seconds until the
entire volume of water is injected.
Continue to operate the engine for at least five minutes to ensure that all of the water is
flushed out of the system.
Not more than three cleaning cycles should be conducted consecutively. Before repeating the
process, continue to operate the engine for at least five minutes to ensure that all of the water
is flushed out of the system.
© Copyright 2017 ABB. All rights reserved.
vessel [dm
]
3
0.4
of pure water.
3
HZTL4031_EN
Water temperature [°C]
5 ... 30
Revision E
Page 49 / 121
Water injection period
[s]
10