Appendix A

Installation Checklist

Table 11. Installation checklist
Y/N
Tasks
Proper clearances for service access have been maintained around equipment.
Equipment is level and mounting fasteners are tight.
If required, piping completed to refrigerant or coolant loop.
All field installed piping leak tested.
If required, refrigerant charge added.
Condensate drain line connected with P-trap and is filled with water.
If required, water supply line connected to humidifier (if required).
If manual cut-off valve is installed, open valve.
Humidifier On/Off/Drain switch is in the on position.
Filter(s) installed.
Duct plenums sealed.
Incoming line voltage matches equipment nominal nameplated rating ±
tolerances.
Main power wiring connections to the equipment, including earth ground, have
been properly installed.
Customer supplied main power circuit breaker (HACR type) or fuses have proper
ratings for equipment installed.
All wiring connections are tight.
If required, control wiring connections completed to field mounted sensors.
Foreign materials have been removed from inside and around all equipment
installed (shipping materials, construction materials, tools, etc.).
Inspect all piping connections for leaks during initial operation.
SS-SVX006C-EN