3.0 OPERATION INSTRUCTION FOR BOILERS WITH CSD-1 CONTROLS (Continued)
3. Press the "RESET" switch to begin the boiler operation. The "STANDBY" pilot light will go
off and the boiler will begin operation.
Daily Startup Procedure
1. Close the manual blowdown valve, if so equipped.
2. Examine that the pilot burner flame is burning. If the pilot burner is out, a five (5) minute
period of complete gas supply shut off is required before relighting.
3. Open cabinet door and turn "ON" the power switch.
The green pilot light will come "ON". Water will begin to enter the boiler. When enough
water has entered the boiler the (amber) "STANDBY" pilot light will come on.
4. Press the "RESET" switch to begin the boiler operation. The "STANDBY" pilot light will
go off and the boiler will begin operation.
Daily Shutdown Procedure
1. Turn "OFF" the power switch. Observe that the burners go off.
2. Open the manual blowdown valve, if so equipped. If the appliance is equipped with an
automatic blowdown solenoid valve, the boiler's contents, water and steam will be blown out
and exhausted through the appliance drain. The cold water solenoid valve will be activated.
Complete Shutdown Procedure
If the appliance is not intended to be operational for a lengthy period, then shut it down
completely.
1. Open the manual blowdown valve, if so equipped.
2. Shut off all supplies of power, gas and water to the appliance.