Operation
Figure 10
shows the SBS data set along with additional ManufacturersAccess() command information
such as individual cell measurements. To view additional Flag and Static data, select the appropriate tab
at the bottom of the SBS Data screen.
Data such as SBS.ManufacturerName( ) is static and does not change. This data is viewed separately
using the Static Data tab available at the bottom of the screen.
To change the height of the Flags/Static Data display, drag the splitter bar (the line that separates the
Flags/Static data from SBS values). To return the splitter bar to its original location, select | View |, then |
Auto Arrange |.
8.2
Setting Programmable bq28400 Options
NOTE: It is very important to have the correct setting of these options to get the best performance.
14
bq28400EVM-001 SBS 1.1 Compliant Tablet PC and Netbook 2-Series Cell
Li-Ion Battery Gas Gauge and Protection
Figure 10. SBS Data Screen
© 2011, Texas Instruments Incorporated
www.ti.com
SLUU494 – February 2011
Submit Documentation Feedback