Summary of Contents for Generac Power Systems RTSF100A1
Page 1
INSTALLATION GUIDE For 100 Amp Automatic Transfer Switch/Load Center Models: 8, 10, 12, 14 and 16 Circuit. Installed with 8, 10, 12, 14, 16 and 17kW Generators. This Automatic Transfer Switch with built-in Load Center includes an Express Install Kit. LISTED •...
Residential Transfer Switch Installation Guide PLEASE NOTE: This installation guide should be used in conjunction with the “Installation and Owner’s Manual” that is fur- nished with the Air-cooled Standby Generator. Please review both manuals prior to installation of the generator and transfer switch. This Automatic Transfer Switch/Load Center is not intended for use with the Liquid-cooled Generator product line.
Residential Transfer Switch Installation Guide 100 Amp Automatic Transfer Designed with installation cost savings in mind! Switch/Load Center with Express Install Kit KIT INCLUDES: THE OUTDOOR CONNECTION BOX WITH FIVE FOOT PRE-WIRED LIQUID TIGHT CONDUIT Mounted outside the home or business nearest the planned generator location.
Page 5
Residential Transfer Switch Installation Guide Site Preparation and Standby Generator Placement Crushed Stone or Pea Gravel 1. PLAN THE LOCATION OF THE GENERATOR. Drill Hole Through House NOTE: Do not place the generator directly under a window. Select an area outside of the home or business nearest the incoming gas service.
Page 6
Residential Transfer Switch Installation Guide From inside the building, feed the end of the 30-foot conduit (INCLUDED and pre-wired from transfer switch) through the wall to the outside. The outdoor connection box must be locked to ensure safety and to discourage tampering. Feed Conduit and Wires 11.
Page 7
Residential Transfer Switch Installation Guide NOTE: Models Balance must be maintained when moving circuit loca- Circuit Circuit Circuit Circuit Circuit tions from main electrical distribution panel to emergency 50A, load center. Circuit breaker positions alternate buss bars Circuits 240V vertically. Circuits sharing a neutral wire should either be moved together to adjacent positions in emergency load 40A, 240V...
Page 8
Residential Transfer Switch Installation Guide THE AUTOMATIC TRANSFER SWITCH/LOAD CENTER IS NOW INSTALLED! If a generator is being installed at this time, proceed 18. Place the generator and mounting pad in the location prepared in steps one through five. to step 19. If a generator will not be installed at this time, perform steps 14 through 17 to complete the pre-wiring project.
Page 9
Residential Transfer Switch Installation Guide Remove the small black cap (covering 1-1/16” diame- 21b. If a leak is located, shut off fuel and disconnect flex- ter hole) from back of enclosure. Remove threaded lock ible piping. Dry the threaded ends and reapply an nut from conduit coupling (with 90°...
Page 10
Residential Transfer Switch Installation Guide Installation Drawing 0H0258-A...
Page 11
Residential Transfer Switch Installation Guide Installation Drawing 0H0258-A...