Commissioning After Taking Out Of Operation - ABB A150-M Series Operation Manual

Turbocharging
Hide thumbs Also See for A150-M Series:
Table of Contents

Advertisement

Operation Manual / A150-M56/66/57/67 - A155-M..
4 Commissioning / 4.3 Commissioning after taking out of operation
4.3

Commissioning after taking out of operation

If present
Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the
u
gas outlet.
Version with compressor wheel cooling:
Remove the locking screw on the cooling air connection and fit the cooling air line.
u
General
Check the exhaust gas pipe before and after the turbine for combustion residues or wa-
u
ter residues and clean it. Remove any foreign objects that may be present.
Check and clean filter silencer or air supply line, and remove any foreign objects that may
u
be present.
Put engine-side oil circulation to the turbocharger into operation.
u
Prepare the turbocharger for operation (see
u
The turbocharger is now ready for operation.
u
© Copyright 2021 ABB. All rights reserved.
Checks before commissioning
HZTL4032_EN
→42).
Rev.R
August 2021

Advertisement

Table of Contents
loading

This manual is also suitable for:

A155-m seriesA150-m56A150-m66A150-m57A150-m67Ht608750

Table of Contents